浅析电网基建项目运转效率
龙源期刊网 http://www.qikan.com.cn
浅析电网基建项目运转效率
作者:胡小琪等
来源:《价值工程》2015年第05期
摘要: 针对电网基建投资项目中存在的问题,开展基建项目过程管控分析。一是分析各类基建项目阶段计划执行情况,评价各类基建工程合理工期,查找进度执行滞后项目;二是分析项目建设中各业务部门协同配合情况,查找内部协作不顺畅环节,查找影响项目进度关键环节及重要因素。
Abstract: For the existing problems of grid infrastructure investment project, this paper
carries out the process management and control analysis of infrastructure project. Firstly, it analyzes the implementation of phase program of all kinds of infrastructure projects, evaluates the reasonable period of various types of infrastructure projects, and finds out the lagging project in
implementation ; secondly it analyzes the collaboration of all business sectors in project construction and looks for unsmooth link of internal collaboration and finds out the key links and important factors affecting the project schedule.
关键词: 电网;进度;合理工期;基建项目
Key words: power grid;progress ;reasonable period;infrastructure projects
中图分类号:TM6 文献标识码:A 文章编号:1006-4311(2015)05-0079-02 1 电网建设中存在的主要问题
①项目建设程序不合规。可能出现工程已经开工,但是线路走廊还未批复,物资招标还没定标,变电站还未确定选址等,使得工程进度拖延,增加成本。②项目过程管理缺乏条理。实施期内存在管理脱节、组织不力、审查不细、把关不严的现象,例如,初步设计过程中经常出现漏项、设计不合理等情况。③外协工作不到位,常使得工期一拖再拖,无法保证,如青苗赔偿等。④与地方政府部门缺乏有效沟通。国家和政府对电网建设项目各个阶段管理工作的要求越来越严格,如土地证等。
2 基建项目过程管控分析
基建工程主要可以分为三类:输变电工程、扩展性技改工程、输变电配套线路工程。输变电工程是指全新工程,其中包含的土建工程大概耗时3-4月,而扩展性技改工程是指在原有变电站新增主变、间隔或线路,其中土建部分耗时大致1-2月。因此,扩展性技改依照输变电工程合理工期执行,但实际工期远短于合理工期。
综上,本文重点研讨输变电工程运转效率问题。