土钉墙方案
金泰广场土钉支护专项施工方案
目 录
一 编制依据···············································4
㈠施工合同·········································4
㈡施工组织设计·····································4
㈢桩位图、基础平面图·································4
㈣勘察设计文件·····································4
㈤现场踏勘资料·····································4
㈥主要规程与规范···································4
㈦有关地方标准、规程································4
㈧有关企业标准·····································4
二 工程概况···············································4
㈠建筑工程概况·····································4
㈡基坑工程概况····································· 5
1、基坑概况·······················································5
2、基坑支护设计要求···············································5
3、场地工程地质条件···············································6
4、工期与质量要求················································ 8
三 施工准备·············································· 8
㈠组织准备·········································8
1
金泰广场土钉支护专项施工方案
㈡技术准备·········································8 ㈢现场准备·········································9 ㈣物资准备········································ 9
四 土钉墙施工·············································9
㈠施工流程···········································9
㈡施工控制要点·······································10
五 降水、排水·············································13
㈠施工排水措施·······································13
㈡施工方面采取的措施·································13
六 施工监测及应急措施····································14
㈠监测内容··········································14
㈡监测点的设置·······································15
㈢监测次数及方法·····································15
㈣监测数据处理及方法·································15
㈤报警值············································15
㈥应急措施··········································16
㈦深层监测··········································18
1、监测方案依据及内容················································18
2、监测点的埋设及施工监测方法········································18
3、监测精度及所采取的技术措施报警值··································19
2
金泰广场土钉支护专项施工方案
4、施工及组织························································20
七 施工机械与人员配备····································20
㈠项目经理部人员配备·································20
㈡施工人员的配备·····································21
㈢主要施工机械配备···································21
八 工程进度计划与工期保证的组织、经济措施·················21
㈠组织措施··········································21
㈡经济措施··········································22
九 质量保证措施和质量通病及预防措施······················26
㈠质量保证措施·······································26
㈡质量通病及预防措施·································28
十 安全、环保、文明施工措施································28
㈠安全施工措施·······································28
㈡环保施工措施·······································30
㈢文明施工措施·······································31
十一 应提交的交工资料····································32
3
金泰广场土钉支护专项施工方案
金泰广场土钉支护专项施工方案
一 编制依据
㈠、施工合同;
㈡、施工组织设计;
㈢、桩位图、基础平面图;
㈣、勘察设计文件:
依据的岩土工程勘查报告为浙江省华夏工程勘察院05年8月提供的《杭
州金泰房地产开发有限公司金泰广场区块岩土工程勘察报告》
㈤、现场踏勘资料;
㈥、主要规程与规范:
《建筑工程施工质量验收统一标准》GB50300-2001
《混凝土结构工程施工质量验收规范》GB50204-2002
《建筑基坑工程技术规范》YB9258-97
《基坑土钉支护技术规程》CFCS96:97
《建筑深基坑支护技术规程》JGJ120-99
㈦、有关地方标准、规程:
㈧、有关企业标准:
企业ISO质量体系管理文件和环境/职业健康安全管理体系文件以及企业项
目管理手册等。
二 工程概况
㈠ 建筑工程概况
拟建的杭州金泰房地产开发有限公司金泰广场区位于萧山区通惠中路
4
金泰广场土钉支护专项施工方案
46-68号,东侧约16.5 m处为丽华公寓,北侧为萧山出入境检验疫局。拟建
工程由浙江省华业建筑设计研究设计,建筑总高99 .99m ,总用地面积7122
㎡,总建筑面积50780㎡,其中地下建筑面积11620㎡,地上建筑面积39160
㎡,住宅建筑面积23240㎡,商场建筑面积15920㎡,建筑占地面积3980
㎡。建筑物地下为1层,地上为31层,均为框架剪力墙结构,筏板基础,
桩型采用钻孔灌注桩.
㈡ 基坑工程概况
1、基坑概况
地下室基坑近似凸字形,长约35m,宽约23m,基坑开挖深度较深,大
面积开挖深度为7.55m 开挖深度在6.35m—9.75m之间。自然地坪面平整相
对标高为-0.300m,相对标高±0.000m相当于绝对标高黄海系标高6.450m。
2、基坑支护设计要求
⑴基坑设计图:
⑵基坑设计要求:
①对原材料的技术要求:
土钉钢筋在使用前应除锈、除油,并做强度检验;优先选用425号以上
标号普通硅酸盐水泥;选用的中、粗砂应干净,含水量不宜大于5%;选用
的豆石,其料径宜在2-4㎜,应干净无杂质;喷射混凝土使用的速凝剂,应
做到与水泥的相容性试验及水泥浆凝效果试验。
②对施工机具的技术要求:
成孔机具:根据施工现场土质情况及环境条件,选择适宜的成孔钻具。
如果钻孔时不出水,可用螺旋钻或洛阳铲;若在涌水、涌砂地层中钻孔,可
选用冲击式锚杆机或地质钻。
注浆泵:其输浆压力和输浆量应符合设计要求;一般将注浆压力控制在
5
金泰广场土钉支护专项施工方案
0.4-0.9Mpa之间。
喷射机:要求密封性良好,输料顺畅,连续均匀。宜采用湿喷型喷射机,
输送压力为0.4-0.6Mpa。
搅拌机:搅拌水泥砂浆时,宜采用强制性搅拌机.
空压机:应分别满足风动成孔钻机和喷射风压的要求.一般选用9m3
以上空压机.
输料管:管壁应能承受1.2Mpa以上的压力,并且有良好的耐磨性.
供水设备:应保证混凝土喷枪之头部有足够的水压力.一般要求水压应
大于空压.
③施工流程及要求
必须遵循施工工艺的要求;必须满足施工方法和施工机械的要求;必须
考虑施工组织的要求;必须保证施工质量的要求;必须考虑施工安全的要求;
必须考虑当地当时的气候条件.
3、场地工程地质条件
⑴地形、地貌及环境条件
拟建场地位于杭州市萧山区通惠中路46-68号,东侧约16.5 m处为丽华
公寓,北侧为萧山出入境检验疫局,西侧紧邻通惠中路。拟建场地原为家私
市场,原有建筑均已拆除,水泥地面已翻松,局部有下水道存在,地势较平
坦,交通方便。勘探点高程在5.71m—6.34m之间。
该工程区在杭嘉湖平原的西南侧边缘,地貌单元属钱塘江冲海积、冲积
平原。
⑵地质条件
根据浙江省华夏工程勘察院提供的工程地质勘察报告,场地内基坑开挖
极其影响范围内土层分布如下:
6
金泰广场土钉支护专项施工方案
①大层:①-1杂填土、①-2素填土,其层份 ,结构松散,均应剥除处
理。
②大层:②-1粉质粘土,性质一般,层厚不大,且不均匀;且不均匀;
②-2砂质粉土,力学性质亦不一般,且局部缺失。以上②-1粉质粘土、②-2
砂质粉土2亚层可结合一大层考虑,但该大层力学性质变化较大,仅可作一
般低荷载轻型建筑的浅基础持力层。
③层;淤泥质粉质黏土,工程力学性质差,属高压缩性软弱土,不宜直
接作为基础持力层。
④大层;④-1粉质黏土,工程力学性质一般,属中偏高压缩性软土;④
-2粉质黏土,工程力学性质尚可,但该土层埋深在10m以下,且层厚不大;
④-3粉质黏土,工程力学性质一般,属中偏高压缩性土。该大层土不宜直接
利用作桩端持力层。
⑤层;黏土,工程力学性质一般,属中偏高压缩性土,不宜直接利用作
桩端持力层。
⑥大层;⑥-1粉质黏土,工程力学性质欠佳;⑥-2黏土,工程力学性质
尚可,但场地北侧缺失;⑥-3黏土,工程力学性质一般,土层厚度变化较大。
该大层只能作为一般建筑的桩基持力层。
⑦层:粉砂,工程力学性质较好,全场分布,但厚度不大,不宜单独使
用。
⑧大层:⑧-1砾砂,工程力学性质尚好,但厚度不大,且局部缺失。⑧
-2圆砾,工程力学性质较好,且厚度大,较稳定,是本场地经济技术较合理
的桩端持力层。故建议采用钻孔灌注桩,并⑧-2圆砾为桩端持力层,桩端进
入持力层深度宜2倍桩径。
⑶地下水
7
金泰广场土钉支护专项施工方案
由于勘探期间正逢干旱与台风期间,地下水位变化较大,测得地下水位埋深在0.60m—3.70m,地下水性质为第四系孔隙水,主要受大气降水补给,水位随季节、气候变化而升降,一般水位年变幅在1.00m—1.50m
4、工期与质量要求
基坑土钉墙围护工程计划工期40天。工程质量应确保围护工程结构可靠,基坑边线与标高应符合设计要求和规范,预留工作面应满足土建工程施工需要。
三 施工准备
按该工程计划安排,要确保在规定时间内完成下列各项施工准备工作,以便及时开工。
㈠ 组织准备
⑴成立项目经理部,建立项目管理机构。
⑵选择技术骨干,组织劳务队及时进场。
项目部人员组成及劳动力需要计划详见附表2、4
㈡ 技术准备
⑴根据施工图、地质报告、合同,在开工前完成施工组织设计的编制工作。
⑵认真进行图纸会审,与业主履行必要的围护平面图的审核手续。项目经理应组织技术人员、施工人员,由工程师进行技术交底、施工组织设计交底和施工承包合同交底,进行质量、安全、文明施工教育。
⑶及时进行必要的材料试验。
8
金泰广场土钉支护专项施工方案
㈢ 现场准备
⑴平整作业场地和临设场地,接通电源、水源。。
⑵排水系统设置:基坑四周支护范围内的地表应加以修整,构筑排水土沟,或者在靠近基坑坡顶宽1-2 m的地面可适当垫高,里高外低,便于径流远离基坑。
⑶放线:与甲方履行正规的测量基准点资料和桩点的交接手续,设置测量控制点,测定围护边线与桩位。控制点应不受施工影响。
⑷摸清施工障碍物,尤其要摸清地下施工障碍物,以便采取措施,防止发生施工事故。
⑸按施工总平面图营建生产临时设施。
㈣ 物资准备
⑴落实并组织施工机具进场。
⑵组织货源,按施工进度要求及时进料。
拟配备的主要施工机械与主要材料需用量详见附表1、表3
四 土钉墙的施工工艺
㈠ 施工流程
1、开挖工作面,修整边坡,埋设喷射砼厚度控制标志。
2、喷第一次混凝土
3、钻孔安装土钉、注浆、安设联接件。
4、安装钢筋
9
金泰广场土钉支护专项施工方案
5、注浆
6、绑扎钢筋网
7、喷第二次混凝土
㈡ 工艺控制要点
1、开挖修整;
⑴开挖顺序
工作面开挖应遵循下列原则;
①分层分段开挖,每段长度6-10m,有建筑物处每段控制在3-4m.
②先开挖道口工作面,待道口土钉完成后再开挖其余部分的工作面。 ⑵分层开挖
①土方开挖应与设置土钉相协调,应按设计规定的分层开挖深度(即土钉竖向距离)和设置土钉的施工顺序分段进行。
②为确保工程质量,上层作业面的土钉与混凝土面层未完成不得进行下一层深度的基坑开挖。
土方开挖到基底标高时,应报请监理、联系土建单位进行垫层施工,尽量减少基底土体的暴露时间。
③修破边
采取任何开挖手段开挖,严禁边壁超挖或松动边壁土体。基坑边壁利用铲锹人工切削修坡,保证边壁平整并符合设计规定的坡度。
④边壁土体暴露时间不得超过规定时限。对于字稳能力差的土体如高含水量的黏性土和无天然黏结力的砂土应立即进行支护。
2、喷第一次混凝土
①喷射混凝土的喷射顺序应自下而上,喷头与受喷面距离宜控制在0.8m
10
金泰广场土钉支护专项施工方案
—1.5m范围内,射流方向垂直指向喷射面,但在钢筋部位,应先喷填钢筋后方,然后再喷填钢筋前方,防止在钢筋背面出现空隙.
②为保证施工时的喷射混凝土厚度达到规定值,可在边壁面上垂直打入短的钢筋段作为标志.当面层厚度超过100㎜时,应分两次,每次喷射厚度宜为50-70㎜.在继续进行下步喷射混凝土作业时,应仔细清除预留施工缝接合面上的浮浆层和松散碎屑,并喷水使之潮湿.
③喷射混凝土终凝后2小时,应根据当地条件,采取连续喷水养护5-7天,或喷涂养护剂.
④喷射混凝土强度可用边长100㎜立方体试块进行测定,制作试块时应将试摸底面紧贴边壁,从侧向喷入混凝土,每批至少留取3组试件,每组3块.
3、成孔(土质好---钻机)
①放样:经纬仪、水准仪、钢卷尺测量并编号。
②允许偏差:孔位不大于150㎜、孔直径为+20-5㎜、倾角不大于3度、空深为+200-50㎜
③清孔;
4、安装钢筋(钢管)
①钢筋调直、除锈、去污。
②尽可能不搭接,用焊接。
③设置定位支架(2-3m),注浆要保护。
④注浆导管与钢筋一起安装。导管端部用2.5m—5.0m用混凝土锚固。
5、注浆
①向孔内注入浆体的充盈系数必须大于1
②注浆用水泥砂浆的水灰比不宜超过0.4—0.45。当用水泥净浆时水灰比不宜超过0.45—0.50,并宜加入适量的速凝剂等外加剂用以促进早凝和控
11
金泰广场土钉支护专项施工方案
制泌水。
③用于注浆的砂浆强度用70*70*70(㎜)立方体试件经标准养护后测定,每批至少留3组试件,每组3块。
6、绑扎钢筋网
①在喷射混凝土前,面层内的钢筋网片应牢固固定在边壁上并符合规定的保护层厚度要求,一般≥25㎜。
②钢筋采用I级钢筋HPB235;6(8)@200*200;加强筋(2根II级钢筋直径20㎜或L100*6)
③钢筋网片可用焊接或绑扎而成,网格允许偏差为±10㎜.钢筋网铺设时每边的搭接长度不应小于一个网格边长或200㎜,如为焊接则焊长不小于网筋直径的10倍.
7、喷第二次混凝土
①喷射混凝土的喷射顺序应自下而上,喷头与受喷面距离宜控制在0.8m—1.5m范围内,射流方向垂直指向喷射面,但在钢筋部位,应先喷填钢筋后方,然后再喷填钢筋前方,防止在钢筋背面出现空隙.
②为保证施工时的喷射混凝土厚度达到规定值,可在边壁面上垂直打入短的钢筋段作为标志.当面层厚度超过100㎜时,应分两次,每次喷射厚度宜为50-70㎜.在继续进行下步喷射混凝土作业时,应仔细清除预留施工缝接合面上的浮浆层和松散碎屑,并喷水使之潮湿.
③喷射混凝土终凝后2小时,应根据当地条件,采取连续喷水养护5-7天,或喷涂养护剂.
④喷射混凝土强度可用边长100㎜立方体试块进行测定,制作试块时应将试摸底面紧贴边壁,从侧向喷入混凝土,每批至少留取3组试件,每组3块.
12
金泰广场土钉支护专项施工方案
五 降水、排水
㈠ 施工排水措施
为了方便施工、保证基坑安全,应采用临时排水措施排除地表水和基坑作业面积水。排水措施包括地表排水,支护内部排水,以及基坑排水,以避免土体处于饱和状态并减轻作用于面层上的静水压力。
⑴地表排水:在基坑外边设置排水沟,使雨水往基坑外流入排水沟内排走。
⑵支护内部排水:在支护面层背部应插入长度为40—60㎝、直径不小于4㎝的排水管,以便将喷射混凝土面层后的积水排出。
⑶基坑排水:为了排除集积在工作面的渗入和雨水,可在土钉工作面内设置临时排水土沟和集水坑,排水沟要离开边壁0.5-1.0m,截面不应过大,坑内有积水时应及时抽出,此排水沟在做完最后一排土钉后,由土建单位做垫层,由图鉴单位做垫层时一起施工.
㈡ 施工方面采取的措施
⑴针对水土作用的防治措施(详见《高成建筑专项施工方案》P77-P79) 在土钉支护工程中,首先要防治水土作用造成的不良影响.目前,在土钉支护工程中采取的措施主要有防、排、堵、挡、抽等方法,同时配合以信息动态施工。
①防,就是预防和防止为主。
②排,就是要对一些水体予以疏导。
③堵,即对部分水体予以封堵,防止渗入或流入基坑。
④挡,修建挡水构筑物以截断水体的径流途径。
13
金泰广场土钉支护专项施工方案
⑤抽,即进行基坑降水。
如果针对边坡两种不同的吸水途径及具体的工程、水文、环境特点采取相应的防治措施,如结合施工以上多种办法,并与动态设计信息化施工相结合,及时对出现的异常情况予以解决,事故是完全可以避免的。
⑵其他施工措施
①采用信息化施工;
②开挖基坑应当按设计步骤和深度进行,严格控制土方分步开挖的高度,并严禁超挖。
③缩短水平方向开挖的分段长度,加快施工节奏以减少暴露时间。
④加强焊接,提高土钉、网体和面板的整洁性。
六 施工监测及应急措施
为确保施工安全和基坑开挖的顺序进行,从围护工程开始施工至地下室底板完工,应进行全过程的施工监测,以便及时掌握施工全过程围护结构、周围土体的受力与变形情况,及时掌握基坑开挖对周围环境、尤其对建筑物、道路的影响程度,以便在监测信息指导下,及时采取有效措施、调整施工方案,避免基坑开挖的重大事故发生,减少事故带来的经济损失和社会影响。 ㈠ 监测内容
土钉围护的施工监测应包括如下内容:
⑴围护体的位移及沉降;
⑵地表开裂状态及周围环境变形;
14
金泰广场土钉支护专项施工方案
⑶基坑渗漏和危及支护安全的水害来源。
⑷基坑底部土体有无隆起,围护外侧土体有无下沉。
㈡ 监测点的设置
⑴监测点、后视点、水准基点应设置在基坑施工影响范围外。
⑵沉降和位移监测点应设在基坑边壁和基坑底部,间距不宜大于30 m. ⑶地表开裂,易采用标记法进行观察和比较,有裂缝时,先测量其宽度并做好记录,然后用水泥浆灌实抹平,必要时可拍照留存。
监测点的设置详见图
㈢ 监测次数及方法
⑴在基坑开挖期间,每天监测次数一次为宜,当位移出现发展趋势或接近预警值时,应加大监测的频率。。
⑵地下室底板完工后可减少监测次数,地下室侧墙完工后停止监测。 ⑶位移观测用Et-02电子经纬仪,沉降观测用精密水准仪,精度为标准二等水准。
㈣ 监测数据处理及反馈
监测数应即填入规定的表格,及时向项目经理报告,定期向业主和监理工程师报告。如发现数据明显变化或临近报警值时应即向项目经理、业主、监理工程师报告。
㈤ 报警值
根据设计规定,报警值如下:
15
金泰广场土钉支护专项施工方案
⑴1-1剖面坡顶水平累计位移40㎜,连续3日位移大于3㎜/d,并且有发展趋势。
⑵其余剖面坡顶水平累计位移60㎜,连续3日位移大于3㎜/d,并且有发展趋势。
⑶地面沉降大于基坑开挖深度的1%。
当位移接近或达到预警值时,或建筑物底部或周围土体出现可能导致剪切破坏的迹象或其他可能影响安全的征兆(如流沙、涌土、隆起、陷落等)时,应立即报警,确定可能采用的应急措施,排除险情。
㈥ 应急措施
1、由于基坑施工受各种客观因素的影响,可能会发生各种险情,为能及时排除险情确保安全,应采取如下应急措施;
⑴成立以项目经理为组长的监控小组,在土方开挖和土钉墙施工阶段进行24 h监控,监控内容包括:墙体水平位移,土钉墙结构变形,周边土体道路及管线的变化。
⑵施工现场准备砂袋。
⑶当围护体位移超过预警值时,使用砂袋压载,防止支护结构位移的发展。
⑷当支护结构的位移增大时,必须时可使用挖土机迅速回填土方反压,以阻止位移的进一步发展,并在位移 处设置超前支护,待稳定后方可继续开挖。
⑸当施工时遇上流沙等土层时,应先打入竖向注浆管进行加固,然后开挖。
2、为了确保安全施工,针对假设出现的几种险情,制订了如下应急措
16
金泰广场土钉支护专项施工方案
施:
⑴围护体滑移的应急措施
根据监测信息,如发现围护体位移超过容许值,应即采取如下措施阻止位移:
①坑外卸载,具体办法同上相关措施。
②在坑内紧急垒堆砂袋或回填压载。
③位移较大并有发展趋势时,可在坑内设置内撑。内撑可为水平撑或斜撑。可用型钢或坚固的木料支撑。
④必要时可采用增加或加长水平土钉的措施,可酌情在松动的围护体内设置竖向土钉(注浆)。
⑵坑底土体隆起的应急措施
①由于围护体滑移造成的坑内土体隆起,应采取处理围护体滑移的措施,同时用重物(叠袋、回填土)压制隆起土体。
②由于淤泥绕过围护体流向坑内造成的土体隆起,应在坑内利用重力压制隆起土体的同时,对围护体进行加固。设置竖向土体(注浆)加固围护体的有效措施。
⑶周边道路或地下管线破坏的应急措施。
造成周边道路或地下管线破坏的直接原因就是围护结构位移或坑底隆起,因此防止发生此种情况的预防措施是:
①加强施工监测,实行信息化施工。
②发生围护位移或坑内土体隆起时,应即采取措施处理。
⑷地表裂缝的应急措施
①及时查明地下裂缝原因,采取相应措施阻止裂缝的发展。
②及时用浓水泥浆灌缝。
17
金泰广场土钉支护专项施工方案
㈦ 深层监测
1、监测方案依据及内容
⑴监测方案的编制依据
①业主提供之总平面布置图;
②业主提供之综合地下管线图;
③业主提供的基坑围护方案及相关图纸;
④有关相类似基坑信息华施工监测实例。
⑵监测项目
为了及时收、反馈和分析周围环境和围护结构在施工中的变形信息,实现信息化施工,确保基础施工安全。综合业主提供的资料,基坑围护方案中对施工监测的要求及本工程特点,考虑本监测工程设置以下几方面的监测内容:
①周围地下管线变形(沉降、位移)监测;
②基坑外地下水位监测;
③深层土体位移(测斜)监测;
④围护墙顶变形(沉降、位移)监测。
2、监测点的埋设及施工监测方法
⑴地下管线监测点
模拟点埋设方法:在地下管线相应上方开挖约30㎝深洞,将顶面刻划“+”的钢筋埋入其中,并用混凝土将其固定;间接点法埋设即直接将顶面刻划“+”的道钉打入地下管线对应上放路面。
测量方法:沉降监测按国家二等水准测量各限差要求进行测量,每次测量宜做到闭合或附合,并符合二等水准的各项精度要求。位移测量采用小角度法。
18
金泰广场土钉支护专项施工方案
⑵周围建筑物沉降监测点
埋设:建筑物监测点直接用冲击钻在外墙体上打洞,并将道钉打入或用“L”形钢筋用水泥砂浆固定。
测量方法:同地下管线监测。
⑶基坑外地下水位监测孔
埋设:采用钻孔埋设。将面包裹工业滤网的PVC水管放入钻孔内用中砂回填至密实再用混凝土封口,以免地表水渗入影响观测,水位孔深度均为10.0m。
测量方法:直接量取监测孔内地地下水位距水位管口的距离。
⑷深层土体位移监测
埋设:采用钻孔埋设。在埋设点上用钻孔,到达设计深度后,逐段安放测斜管,顶底封闭,接头处用自攻螺钉拧紧,并用胶布密封。安放完毕后用膨润土及黄砂回填,直至钻也隙密实为止,并用混凝土封口,孔深根据基坑深度确定。测斜管内的十字导槽必须有一组垂直于基坑边线。
测试方法:先以测斜孔底为起测基准,以0.5 m 点距由下向上进行测试,测试数据处理时均用经纬仪测得的测斜管口的位移值进行测斜成果的修正,经计算处理产生测斜曲线及数据表。
3、监测精度及所采取的技术措施、报警值
⑴技术措施
①为了确保各项监测项目的精度,投产的仪器必须按规定内容检查标定其主要技术指标,仪器检查合格后方可使用,并做好记录归档。遇特殊情况(受震、受损)随时检查、检定。不合格仪器坚决不能投产使用。
②水准测量宜采用闭合或附合路线观测方法。
③尽量做到测量定人,定仪器;观测数据不得随意涂改,测量数据有疑
19
金泰广场土钉支护专项施工方案
问时,因做至反复观测寻找问题的原因。
④各监测项目变形量或测量值接近或到达报警值时,应及时发出预警报告或报警,并提请业主及有关单位注意。
⑵报警值
①地下管线监测报警值由专业管线公司给定,具体报警值为累计变量≥±10㎜,日变量≥±3㎜。
②其他有关监测内容报警值敬请设计单位确定,一经确定,我司将严格按照标准执行。
4、施工及组织
⑴监测频率
基坑开挖至底板完成其间,地下管线变形监测2次/ d、基坑外地下水位监测1-2次/d、深层土体位移监测1-2次/ d、围护墙顶面变形监测1-2次/ d。
地下室结构至±0.00其间,地下管线变形监测1次/3d、基坑外地下水位监测次/ 3d、深层土体位移监测1次/ 3d、围护墙顶面变形监测1次/3d。
⑵提交的测试成果
建立监测成果及时汇报制度。正常情况下当天的监测成果第二天呈报业主和有关部门,叙述监测点(孔)当次及累计的成果动态及有关注意问题。如遇报警情况,先当场口头通知同时4 h内提交正式报警资料。
七 施工机械与人员配备
为确保按合同工期完工,应配备足够的施工机械和人员。
㈠ 项目经理人员配备
成立项目经理部,由项目经理部组织工人员进行履行经营。
20
金泰广场土钉支护专项施工方案
㈡ 施工人员的配备
劳务队由本公司技术精、作风过硬的生产骨干组成。劳务队人员施工高
峰时24人。
㈢ 主要施工机械配备
配备施工机械应本着满足工期和适应工程特点的需要。
八 工程进度计划与工期保证的组织、经济措施
㈠ 组织措施
1、公司的准备配备装饰施工经验丰富、技术实力强的项目管理班子,
中标后立即可投入人力、物力,及时进场组织施工。
2、充分发挥我公司施工组织管理的优势,公司各职能部室对本进度计
划全力支持,由各级管理人员对各道工序进行全过程控制,在做好成品保护
的前提下,促使各分部分项工序以最大限度进行合理的交叉施工,保证施工
流水能按计划正常运转。
3、加强施工中的过程控制,严格“三检”制,提高一次交验合格率,避免
不必要的返工返修,延误工期。
4、加强工厂化施工,门框、造型门、各种木线、石材及其他专业设备
均可安排进行工厂化加工,现场安装,这样既可保证质量又确保施工工期。
5、暖卫、电气、通风、空调等设备安装工程与其他各分部工程配合土
建穿插作业,尽可能不占用整体工期。
21
金泰广场土钉支护专项施工方案
6、在总体计划控制下,制定月计划、周计划,并按计划每周召开一次
现场协调会,及时解决劳动力、施工材料、图纸、资金、成品保护等方面存
在的问题,每月报详细计划,认真听取业主及监理工程的意见,以确保工期。
7、施工进度计划责任落实到人,工种、作业队,实行奖罚制度,在保
证质量的情况下,上道工序进度不能影响下道工序进度。
8、生产上要根据进度计划及现场实际情况,合理安排各工种进退场时
间及劳动力用量,材料部门做好材料计划并使材料、工具及时到位,技术、
质量各部门也要密切配合,做到随叫随到,不影响生产。
9、对工程施工的问题和困难做好充分的思想准备和技术准备,图纸技
术分析、细部分项施工计划、资料管理、施工管理、放线核线、材料确认和
定货、场外加工安全保护等准备工作,将及时配合施工计划进行安排,为工
程施工顺利进行提供强有力保障。
㈡ 经济措施 确立了工程项目的进度控制目标后,还应在工程开工前,依据合同条款、
技术规范和施工方法等拟定一个项目的实施计划,再结合业主的资金筹措能
力,建立一个有关键线路的总网络计划经济分析图以此作为进度计划执行的
依据。
①结合工程特点用网络计划进行多方案比较以确定最低总成本的工期
目标和实施计划从而保证总体计划的实现,使进度的经济性从根本上得以落
实。
②根据工期—成本优化后的最优工期编制网络进度计划并把资金目标
进行层层分解绘制工程实际进度与计划进度比较图,发现偏差,及时调整,
对确因某种原因完成不了的目标,采用滚动计划法进行调整,并分析没有完
22
金泰广场土钉支护专项施工方案
成的原因,落实解决措施,争取在以后的工序中,用较少的成本增加值补回
所拖欠的进度以确保进度目标的实现。
③建立进度控制的经济保证体系实行程序化控制。根据进度目标的经济
性要求编制程序框图,然后按框图中所规定的内容,在工序开工前、施工中
对需要控制的各个环节进行认真检查,发现问题,及时解决。
④合理配置资源。资源的供应与均衡问题是制约工期及进度的重要因素
之一资源的供应与均衡是一种动态平衡,应尽可能减少因资源短缺对工期的
影响,因此,一方面要求业主要及时筹措资金以确保施工用款;另一方面要
对承包商的施工组织及工程进度进行监督管理。
⑤建立控制工期的奖罚机制并及时兑现。为了鼓励承包商对进度控制的
积极性对关键线路上的工作制定提前或滞后的奖罚对策,对非关键线路的工
作,工期提前了不奖,但滞后了要罚,这样才能按为确保按合同工期完工,
应配备足够的施工机械和人员。
成立项目经理部,由项目经理部组织工人员进行履行经营。
劳务队由本公司技术精、作风过硬的生产骨干组成。劳务队人员施工高峰时
24人。
配备施工机械应本着满足工期和适应工程特点的需要。
1、公司的准备配备装饰施工经验丰富、技术实力强的项目管理班子,
中标后立即可投入人力、物力,及时进场组织施工。
2、充分发挥我公司施工组织管理的优势,公司各职能部室对本进度计
划全力支持,由各级管理人员对各道工序进行全过程控制,在做好成品保护
的前提下,促使各分部分项工序以最大限度进行合理的交叉施工,保证施工
流水能按计划正常运转。
23
金泰广场土钉支护专项施工方案
3、加强施工中的过程控制,严格“三检”制,提高一次交验合格率,避免
不必要的返工返修,延误工期。
4、加强工厂化施工,门框、造型门、各种木线、石材及其他专业设备
均可安排进行工厂化加工,现场安装,这样既可保证质量又确保施工工期。
5、暖卫、电气、通风、空调等设备安装工程与其他各分部工程配合土
建穿插作业,尽可能不占用整体工期。
6、在总体计划控制下,制定月计划、周计划,并按计划每周召开一次
现场协调会,及时解决劳动力、施工材料、图纸、资金、成品保护等方面存
在的问题,每月报详细计划,认真听取业主及监理工程的意见,以确保工期。
7、施工进度计划责任落实到人,工种、作业队,实行奖罚制度,在保
证质量的情况下,上道工序进度不能影响下道工序进度。
8、生产上要根据进度计划及现场实际情况,合理安排各工种进退场时
间及劳动力用量,材料部门做好材料计划并使材料、工具及时到位,技术、
质量各部门也要密切配合,做到随叫随到,不影响生产。
9、对工程施工的问题和困难做好充分的思想准备和技术准备,图纸技
术分析、细部分项施工计划、资料管理、施工管理、放线核线、材料确认和
定货、场外加工安全保护等准备工作,将及时配合施工计划进行安排,为工
程施工顺利进行提供强有力保障。 确立了工程项目的进度控制目标后,还应在工程开工前,依据合同条款、
技术规范和施工方法等拟定一个项目的实施计划,再结合业主的资金筹措能
力,建立一个有关键线路的总网络计划经济分析图以此作为进度计划执行的
依据。
24
金泰广场土钉支护专项施工方案
①结合工程特点用网络计划进行多方案比较以确定最低总成本的工期
目标和实施计划从而保证总体计划的实现,使进度的经济性从根本上得以落
实。
②根据工期—成本优化后的最优工期编制网络进度计划并把资金目标
进行层层分解绘制工程实际进度与计划进度比较图,发现偏差,及时调整,
对确因某种原因完成不了的目标,采用滚动计划法进行调整,并分析没有完
成的原因,落实解决措施,争取在以后的工序中,用较少的成本增加值补回
所拖欠的进度以确保进度目标的实现。
③建立进度控制的经济保证体系实行程序化控制。根据进度目标的经济
性要求编制程序框图,然后按框图中所规定的内容,在工序开工前、施工中
对需要控制的各个环节进行认真检查,发现问题,及时解决。
④合理配置资源。资源的供应与均衡问题是制约工期及进度的重要因素
之一资源的供应与均衡是一种动态平衡,应尽可能减少因资源短缺对工期的
影响,因此,一方面要求业主要及时筹措资金以确保施工用款;另一方面要
对承包商的施工组织及工程进度进行监督管理。
⑤建立控制工期的奖罚机制并及时兑现。为了鼓励承包商对进度控制的
积极性对关键线路上的工作制定提前或滞后的奖罚对策,对非关键线路的工
作,工期提前了不奖,但滞后了要罚,这样才能
时完成或提前完成工期目标。
⑥实行目标管理对成本斜率K较大的工作建立目标控制点作为进度目
标经济性控制的重点。对可能影响工期经济性的“风险区”进行预控和跟踪控
制,并将它们标在网络图上,施工接近风险区时,尽早采取有效措施,防范
因进度拖延造成的经济损失。
按照上述措施对进度计划的执行过程进行连续的监测检查、动态控制,
25
金泰广场土钉支护专项施工方案
以便尽早发现问题,及时纠偏,确保工程进度目标的顺利实施,获取工程项
目最佳的经济效益。
九 质量保证措施和质量通病及预防措施
㈠ 质量保证措施
为确保工程质量,必须严格按设计要求、规范和质监站的有关规定组织
施工,必须认真按本施工组织设计的有关规定组织施工,同时必须实施如下
质量保证措施:
1、重要保证措施
基坑置于淤泥层和淤泥质黏土层,该土层含水量较高,土质差。因此必须
引起高度重视,认真采取如下措施确保围护安全。
⑴确保喷射面层质量,防止外部水浸入坑内,保护土体结构不受破坏。
⑵力求缩短边壁暴露时间。根据土钉的施工进度适当调整工作面开挖速度,
以便在工作面开挖24~36h内完成土钉施工。
⑶要确保土钉质量。尤其进入淤泥质粉土层后,必须确保土钉长度、角度、
注浆和混凝土面层的工程质量,减少围护体的位移量,以便使围护体具有可
靠的稳定性,有效地保护围护体自身的安全。
⑷及时进行抗拉拔试验,加强施工监测,实行信息化施工,根据监测结果及
时调整技术参数和实施加固措施,确保工程质量。
⑸根据地层土质情况适时调整设计,以便既能有可靠的结构稳定性,又能降
低工程成本
⑹注意保护围护周边的管线,施工前摸清其走向和位置,土钉施工时尽量避
开。
2、常规保证措施
26
金泰广场土钉支护专项施工方案
⑴该项工程为确保安全施工,必须严格按施工规范和验收规范组织施工。
⑵认真贯彻质量管理责任制,建立健全质量保证体系,责任到人,各尽其责。
⑶严格把好材料进货关,严格水泥的进货检查,不合格的水泥不得利用。
⑷测量定位必须准确无误,应认真对大样进行复核。
⑸加强计量管理。要责成专人负责施工过程的计量管理,随时检查计量器具,
认真计量,确保浆液质量。
⑹行工序的质量跟踪管理。从测量控制——放样——土钉施工和基坑开挖的
全过程都要实行专责质量跟踪管理,逐道工序都要把住质量关,前道工序质
量达不到质量要求,后道工序不准施工。
质量的跟踪管理要坚持实行质量自检、互检和检验的管理办法。
⑺要重点抓好质量管理的关键工序和技术参数:
①定位;
②土钉标高和间距、土钉长度,土钉打入角度;
③土钉接长焊接质量及面层钢筋铺设质量;
④土钉与面层钢筋及加强筋的连接质量;
⑤注浆的质量;
⑥确保做到压顶板和土钉墙平整。
27
金泰广场土钉支护专项施工方案
㈡ 质量通病及预防措施
质量通病原因分析及预防措施表
十 安全、环保、文明施工措施
㈠ 安全施工措施 ⑴周边设置防冲墙和封闭式维护栏杆,并在维护栏杆上涂红白标记防止
物体坠落伤人;
28
金泰广场土钉支护专项施工方案
⑵加强排水沟的排水设施管理;
⑶有专人指挥挖土,严禁超挖,确保安全施工;
⑷严格监测数据来指导施工,加强信息化施工管理,确保工程安全,认真贯彻“安全第一、预防为主”的方针,坚持“谁施工、谁负责“和“管生产必须管安全“的原则,根据”国务院关于加强企业生产中安全工作的几项规定“,结合实际和本工程特点,组成由项目部主要负责人、专职安全员、项目部和班组兼职安全员以及工地安全用电负责人参加的安全生产管理网,执行安全生产责任制,明确各级人员的责任,抓好本工程的安全生产工作。
⑸工程实施前,对参与本工程施工的全职人员(包括民工)进行安全生产的宣传教育,组织职工学习国务院、省、市和公司颁发的有关安全生产的《规定》、《条例》和《安全生产操作规程》,并要求职工在施工中严格遵守有关文件的规定。
⑹工程施工前,对投入本工程施工的机电设备和施工设施进行全面的安全检查,未经有关安全部门验收的设备和设施不准使用,不符合安全规定的地方立即整改完善。并在施工现场设置必要的护栏、安全标志和警告牌。
⑺工程实施时,严格按照经公司审定的施工组织设计和安全生产措施的要求进行施工,操作工作必须严守岗位履行职责,遵守安全生产操作规程,特种作业人中应经培训,持证上岗,各级安全员要深入施工现场,督促操作工人和指挥人员遵守操作规程,制止违章操作、无证操作、违章指挥和违章施工。
⑻工程实施时,每周召开一次安全例会,检查安全生产措施的落实情况,研究施工中存在的安全隐患,及时补充完善安全措施。
⑼经常保养施工机具,保证安全装置灵敏度可靠,防护罩完好无损,同时搞好安全用电管理,保证变电配电间达到“四方”要求,输电线路、配电
29
金泰广场土钉支护专项施工方案
箱、漏电开关的选型正确、敷设符合要求,电器设备和照明灯具有良好的接地、接零保护,并在可能受雷击的场所设置防雷击设施。
⑽重视个人自我防护,进入工地按规定佩带安全帽,进行高空作业和特殊作业前,先要落实防护设施,正确使用攀登工具,安全带和特殊防护用品,防止发生人身安全事故。
⑾按照防火防爆的有关规定设置油库、危险品等临时性构筑物,易燃易爆物品堆放间距和动火点与氧气、已火块的间距要符合规定要求,严格执行动火作业审批制度,一、二、三级动火作业未经批准不得动火,临时设施区要按照规定配足消防器材。
⑿工地上设置救护室,配备医务人员,落实保健措施,作好除害灭病和饮食卫生工作。
⒀实施无工程事故和重点设备、人身伤害无事故的安全目标。
㈡ 环保施工措施
⑴场内砌筑1容量为100M3的废浆池,保证白天桩机施工生产的泥浆排放。
⑵利用密封罐车日夜排污,天亮前必须将废浆池排干,以保证高峰期不排废浆装运。
⑶按交管部门要求的规定时间内用密封罐车进行运输,把废浆运至规定地点进行排放,在运输公路不得有泥浆流淌,在大门口进出口及有污染的公路上必须及时清理干净。
⑷为确保泥浆外运正常,施工前应在交管部门办理好通行证,并严格执行交通规则和有关规定,确保泥浆正常外运。
⑸施工道路及堆场进行硬质处理,并铺设明沟排水。
30
金泰广场土钉支护专项施工方案
⑹主施工道从桩外通过,铺设路面,同时尽可能避免车辆进入,污染施工道。
⑺及时清除施工场地的溢浆、污泥。
⑻每天对施工车进行清理,避免排污车辆污染主要施工完毕、轨道拆除后,立即清理出施工场区。
⑼运输车进出场均要检查,做到不将污染物带出施工场地 ⑽严禁污水、废水外流或堵塞下水道,并排入河道。
㈢ 文明施工措施
⑴编制施工组织设计时,把文明施工列为主要内容之一,制定出以“方便人民生活,有利于生产发展,维护市容整洁和环境卫生“为宗旨的文明施工措施。
⑵本工程建设将全面开展创建文明工地活动,切实做到“两通三无五必须”。(即:施工现场人行道畅通;施工工地沿线单位和居民出入通道畅通;施工中无管线事故;施工区域与非施工区域必须严格分隔;施工现场必须堆放整齐合理,必须开展以创建文明工地为主要内容的思想政治工作)。 ⑶挂牌出示施工现场总平面图布置图,标明工程名称、建设、监理、设计、施工单位名称、工期、工程主要负责人姓名和监督电话。自觉接受社会监督。
⑷施工场地采取全封闭隔离措施,工地主要出入口设置交通指令标志和警示灯,保证车辆和行人的安全。
⑸实施施工现场平面管理制度,各类临时施工设施、施工便道、加工场、堆物场和生活设施均按经总公司审定的施工组织设计和总平面布置调整图,报上级部门审批,未经上级部门批准,不得擅自改变总平面布置或搭建其它
31
金泰广场土钉支护专项施工方案
设施。
⑹施工现场设置以明沟、集水池为主的临时排水系统,施工污水经明沟引流、集水池沉淀澄清后,间接排入下水道;同时落实“雨季防涝“措施,配电雨季施工防护器材和值班人员,作好雨季地下室施工工作。
⑺工作材料、成品构件分门别类,有条理地堆放整齐;机具设备定时定人保养,保持运行整洁,机荣正常。
⑻施工中严格按照经审定的施工组织设计实施各道工序,工人操作要求达到标准化、规范化、制度化、做到工完料清,场地上无淤泥积水,施工道路平整畅通,实现文明施工。
⑼加强土方施工管理,防止泥浆污染场地。
⑽设立专职的“环境保洁区”,负责检查、清除出场车辆上的污泥,清扫污染的马路,做好工地内外的环境保洁工作。
⑾工地上配齐厕所、饮用水供应点等生活设施,并指定卫生制度,定期进行大扫除,保持生活设施整洁卫生和周围环境整洁卫生。
⑿项目部设文明施工负责人,每周召开一次关于文明施工的例会,定期与不定期检查文明施工措施落实情况,组织班组开展“创文明班组竞赛活动”,经常征求建设单位、施工和监理对文明施工的批评意见,及时采取整改措施,切实搞好文明施工。
十一 应提交的交工资料
施工过程中要及时收集、整理各类原始资料,做到完整、真实和整洁。竣工时,按公司“工程交工资料标准”汇总装订,送交有关单位和部门。 应提交的交工资料主要有:
32
金泰广场土钉支护专项施工方案
⑴施工组织设计 ⑵工程用料的质量资料 ⑶施工过程的施工管理资料 ⑷工程质量资料 ⑸工程交工验收书
33
金泰广场土钉支护专项施工方案
附表1:
34
金泰广场土钉支护专项施工方案
UP=0.5×{( )×0.1+( )×0.3+( )×0.6}+0.5×( )=
教师评语
指导教师签名:
35