某七层住宅楼安装工程施工组织设计_secret
施工组织设计
摘 要:
该施工组织设计包括强电系统、弱电系统、防雷接地、生活给排水、宽带、电视电话等的施工设计及施工方案。
关键词:建筑电气、施工组织设计、施工方案、安装施工、建筑安装施工。
目 录
一、编制依据··············································6 二、工程概况··············································6 三、施工组织机构与职责····································8 1、项目部组织机构示意图······································8 2、兼职情况说明·······················································9 3、职责····················································9 四、施工部署···············································10 1、施工顺序·················································10
2、施工部署·················································11 3、工期计划安排················································11 4、劳动力组织···············································11 五、基础设施和工作环境····································13 1、设备需用量及劳动力等供应计划···································13 2、全用电技术措施··············································13 3、临时设施施工计划············································15 六、施工技术措施·············································15 1、主要分部分项工程施工方法·····································15 2、治理质量通病措施···········································18
3、各工种施工配合··············································19 七、施工质量保证措施········································19 1、质量管理目标···············································19 2、质量保证体系···············································
20
1
3、以顾客为关注焦点············································21 4、文件要求··················································21 5、人力资源控制···············································24 6、采购······················································24 7、机械设备、周转器材及监视和测量装置···························24 8、施工过程控制···············································24 9、产品监视和测量·············································25 10、分析改进·················································26 八、环境安全管理·············································26 (一)环境安全管理组织·········································26 (二)环境安全管理············································26 (三)环境保护················································29 (四)、文明施工管理···········································30 九、工期保证措施·············································31
十、降低成本措施············································31 十一、施工平面布置图········································31
2
某23#住宅楼
质量计划/施工组织设计、环境安全管理方案
一、编制依据:
1、工程合同:某23#住宅楼工程施工合同以及与土建公司签定的《内部分包协议》。 2、施工图纸:某23#住宅楼安装工程施工图纸。 3、国家现行的有关标准及规范
4、《质量计划/施工组织设计编制规定》QWJ/III JS.01-2002
5、《环境安全手册》ESWJ/I01-2005 6、《程序文件》(环境安全管理体系) 7、《中华人民共和国安全生产法》 8、《建筑工程安全检查标准》
9、国家、省、市有关质量及环境安全方面的其他标准、规定和规范。 10、有关支持性文件。
二、工程概况:
1、工程名称:某23#住宅楼; 2、工程结构:框架结构;
3、总建筑面积:590.4平方米。共七层; 4、质量标准:合格; 5、建设单位: 设计单位:
3
监理单位:
6、开工日期: 年 月 日 7、计划竣工日期: 年 月 日
8、工程范围及内容
(1) 建筑给排水与采暖部分 ①生活给水系统 ②生活排水系统 ③采暖系统
(2) 建筑电气部分 ① 普通照明系统 ② 防雷及接地系统 ③ 弱电系统 ④ 动力系统 10、工程概况:
(1)建筑给排水与采暖部分
1生活给水系统:自来水供水系统由市政自来水管网直供一层至七层; ○
管材及连接方式:给水管采用“LP抗菌PP-R引水管”及配件(压力等级1.60Mpa),热熔连接或丝接;消防管采用热镀锌管管,暗管刷油沥青二度,明管刷银粉二度。
2生活排水系统:本工程污水与废水为合流系统,室内±0.000米以上污废水采用重力○
自流排出。生活污废水经化粪池处理后排入市政污水管网。
管材及连接方式:室外排水干管采用混凝土管,埋地部分及排出管出屋面部分采用铸铁管,其他均采用芯层发泡UPVC塑料管及配件,铸铁管刷沥青二度。
③采暖系统:本工程为60-50℃热水地板辐射加散热器采暖系统,工作压力为0.4Mpa,热损耗为256.6KW。
管材及连接方式:采暖管道均为热镀锌钢管,立管至集分水器及集分水器至各房间加热管均采用交联聚乙烯(PE-X-A)管。 (2) 建筑电气部分 ① 供电系统:
A负荷等级:本工程的负荷等级为三级。
B供电电源:由 380V/220V三相四线制电源供电,电源进线采用VV22-!KV电力电缆穿镀锌钢管G埋地引入,埋深0.7米,系统采用TN-C-S形式。总接地线在电源进线处同电源零线一起须与总等电位端子板连接,配电箱加装电涌保护器SPD,SPD两端引线总长不超过0.5米。进出建筑物的金属管道与构件与总等电位端子板连接。
C计量方式和无功补偿:每户单设电表与一层总配电箱内进行计量。无功在低压侧
集中补偿。功率因数大于0.9。
D供电方式:照明配电系统采用放射式配电方式。 E导线选择及线路敷设:住户干线采用BV型铜芯导线。所有干线均穿PVC管埋地暗敷及墙内暗敷,照明支线采用BV-500聚氯乙烯绝缘护套铜芯导线穿PVC管沿墙及楼
4
板暗敷;多根BV导线共管敷设时,穿管管径为,三根及以下PVC20
,四根至六根为PVC25,六根以上为PVC32。 ① 电照系统:
储藏室及房间内用2*36W荧光灯,厨房及卫生间选用防水防潮吸顶灯,楼梯为浅扁圆吸顶灯。除图纸注明外,开关、插座分别距地1.4米、0.3米暗装。卫生间插座采用防潮防溅型面板,距地1.8米;热水器插座距地2.3米暗装;客厅空调插座为距地、顶0.3米处各设一个;卧室空调插座为距地2.0米;油烟机插座距地2.0米暗装;1.8米以下插座均采用安全型。照明配电箱底边距地0.8米、1.8米,总、局部等电位箱底边距地0.5米。
② 防雷、接地及等电位连接:
防雷等级:本工程的防雷等级为三类。
避雷装置采用16×24网格的避雷网系统。凸出屋顶的所有金属件与构筑物应与避雷网相接,防雷系统所有节点均应电气焊焊接并防腐。利用外墙内主筋作引下线,每条引下线距地1.8米做测试连接板。借基础圈梁作自然接地体,防雷接地与总等电位端子板连接,总接地电阻小于等于1欧姆,否则增加人工接地装置。引下线、基础圈梁钢筋及人工接地体可靠焊接。 ③ 弱电部分
1、电话系统:
电话外线采用HYA型电话电缆穿G管埋地引入,埋深0.7米,组线箱设在中间单元储藏室层,储藏室层其他单元设分组线箱安装高度1.0米,单元之间采用HJPYV型电话电缆穿G敷设,其他电话线路采用RVB-2×0.5型电话线穿PVC管暗设,电话终端接线盒安装高度0.3米。 2、宽带网系统:
宽带网系统采用GYSLA8B型光缆穿G管埋地引入,引至中间储藏室层。在第中间单元储藏室层设接入箱,其他单元储藏室层设分线盒。除进线外,其他线路采用5类UIP非屏蔽缆穿PVC管敷设,微机终端插座安装高度0.3米。 3、电视系统:
电缆电视系统采用412铝管电缆G40-DA,埋深0.7米,集线器箱设在中间单元三层。安装高度下底距地1.8米,在三层其他单元设集线器箱,安装高度距地1.8米。其他各层设分线盒,线路采用SYW穿PVC管暗设,终端口安装高度0.3米。 4、楼宇对讲系统
楼宇对讲系统采用直按式,在楼梯入口处设室外主机,由不间断电源供应器供电。不间断电源供应器由220V/50HZ电源供电,输出电源DC18V,安装高度1.6米。室内采用壁挂式非可视室内机,安装高度1.6米。 11、工程特点:本工程工期紧。 12、关键工序:
①电气配管、管内穿线为关键工序,在施工前编制详细的安全技术交底。 ②管道保温为关键工序。
三、施工组织机构及职责
1、 项目部施工组织机构示意图:
安装分部施工组织机构示意图
2、 兼职情况说明:
(1) 负责人兼任安装分部环境安全管理员。
(2) 管道、电气技术员兼任安装分部核算员及质检员。 3、 职责
(1)项目部职责:
a、 负责所施工工程项目的全面管理;
b、负责质量计划/施工组织设计的编制和实施; c、负责施工现场的物资管理;
d、负责施工现场安全防护和文明施工管理; e、负责劳务分包和工程分包的现场管理;
f、负责现场设备、计量器具的使用、维修和日常保养; g、负责施工记录的收集整理;
h、负责现场轻微、一般不合格品的处置;
i、负责施工现场产品(物资、成品、半成品)的防护; j、负责检验批、分项工程的验收;
K、负责施工过程各种信息的数据分析,并采取纠正/预防措施。 (2)项目负责人职责:
a. 负责与建设单位、监理单位、总包单位及上级主管部门的联系,及时反馈顾客 信息,办理工程变更和分部分项工程验收;
b. 负责对新工人进行质量、安全方面的培训;
c. 负责掌握、控制安装工程的成本情况并进行调整;
d. 主持全面质量、安全管理工作,定期召开质量、安全分析会,制定管理措施并落 实管理责任;
e. 负责按照经批准的质量计划/施工组织设计合理组织施工; f. 根据工程进度提出劳动力及设备计划报分公司批准; g. 负责落实成品、半成品的保护措施; h. 负责纠正预防措施的实施;
i. 负责材料的监督管理,严禁使用不合格材料并对此负责。 (3)项目保管员职责:
a. 按照材料验收标准进行现场材料的验收,把好材料的质量关、数量关、单据关, 做好验收记录,保存有关料具的证明材料;
b. 及时办理材料的入库管理,登记帐卡做好标识;
c. 合理贮存、堆放、保管材料,保证仓储材料的安全、不变质、不变形,保持仓 库的清洁卫生;
d. 材料出库手续准确,出库后及时登帐填卡,保证帐物卡相符;
e. 不得私自外借料具,料具要进行定期盘点,保证料具数目清、账目清; f. 检查施工现场材料的使用,杜绝材料的浪费和流失。 (4)安全员职责:
a. 认真贯彻执行国家有关安全生产的方针、政策、法令、法规和公司安全生产规 章制度,做好安全生产的宣传教育和管理;
b. 监督检查施工现场的安全生产情况,发现安全隐患及时提出并监督整改; c. 有权制止违章指挥、违章操作、违反劳动纪律的行为; d. 做好新工人入厂的安全教育;
e. 认真开展各项安全生产竞赛达标活动;
f. 发生事故,保护好现场并在规定的时间内上报公司有关部门; g. 参加安全事故的调查、分析、处理。 h. 负责项目安全管理资料的收集整理。 (5)技术员职责:
a
、全面负责本工程的技术管理工作,认真落实各项管理制度和措施;
b、 制定技术措施,开展全面质量管理,指导QC小组活动,积极采用新工艺、 新技术、新材料;
c、参加图纸会审、编制质量计划/施工组织设计; d、办理日常的变更记录、隐蔽记录、施工日志等技术资料;
e、向材料员提供材料总计划和月材料计划,负责工程预算及竣工结算的编制审定, 参与成本核算及成本分析;
f、对施工队进行技术、质量、安全交底,并在施工中进行指导和监督; g、领导现场试验管理工作,负责将需做化验的材料送质检部门化验; h、领导施工测量放线工作,复核原始测量数据,并做好隐蔽记录;
i、负责工程图纸翻样、外加工计划、加工图的编制;
j、负责技术资料的收集、整理、归档工作。编制竣工图,做好工程技术总结。 (6)质检员职责:
a、 负责监督、指导项目部,认真执行施工规范、操作规程。确保工程质量目标的
实现。
7
b、 配合项目部其它岗位人员,每日对所施工的部位进行检查,认真执行“三检查” 和样板制,对不符合标准的分项,不允许进入下一道工序。同时根据检查情况对班组提出奖罚。
c、 协助项目经理进行检验批、分项及分部的检验评定,及时了解甲方和监理单位对 工程质量的满意程度。
d、 负责收集整理项目质量管理资料。 (7)设备员职责:
按《程序文件》中的有关要求对施工现场的设备及计量器具进行管理。 (8)核算员职责:
负责工程成本的分析控制,及时向施工负责人提供成本情况。
四、施工部署:
1、施工顺序
(1)电气照明、弱电系统
施工准备→预埋线路保护管→测量放线→安装盒、箱体→管内穿线→第一次电气绝缘电阻测量→安装各种开关、插座、灯具、配电箱→第二次电气绝缘电阻测量→ 通电调试运行试验
(2)防雷接地系统安装程序:
施工准备→焊接基础接地极→焊接防雷引下线→焊测试点→安装屋面避雷带 →测量接地电阻
(3)室内给水系统的安装程序:
1自来水hanjie系统:安装准备→预制加工→引入管安装→水平干管安装→立管安装→○
支管及配件安装→管道试压→管道冲洗消毒→系统通水。 2太阳能热水系统:○安装准备→支座架安装→集热水器安装→辅助设备安装→配水管路安装→管路系统冲洗→温控仪表安装→防腐和保温→系统调试运行 (4)室内生活排水系统的安装程序:
施工准备→埋地横管→灌水试验及隐蔽→放线定位、支架安装→ 排水立管→每层排水横支管→器具支管→通球试验→通水试验。
(5)卫生器具安装程序:
卫生器具预装——卫生器具配件安装——卫生器具安装——外观检查——满水试验——通水试验。
(6)采暖系统安装: 1地板辐射采暖系统:○放线定位→预制加工→管道敷设→集配装置安装→管道连接→初次试压、冲洗→管道保温→管道填充→二次试压→供暖调试
2散热器采暖系统:散热气组对→散热器单组试压→支、托架安装→散热器安装 ○
2. 施工部署
(1)管道安装主要工程内容有:室内给水系统、采暖系统、室内生活排水系统。
1预留预埋阶段。由技术员出具预留预埋交底,出具预埋预留的位置尺寸图特别是○
卫生间管道洞口的预留预埋,一定要与土建单位紧密配合。结合土建相应的设计变更,与
设计联系,出具相应的设计变更。尽量避免因遗漏而发生的打砸现象。
2
埋地、地沟管道安装。此项工作在土建主体竣工及地面内较清洁时进行,避免土○
建在此时施工对管道的污染或损坏。
8
○
3隐蔽及试验。埋地管道在土建回填完毕后开挖管沟。埋地管道在安装完毕后,必须做灌水、水压试验,经建设单位、监理单位、班组检验合格后办理隐蔽记录,各方签字认可。试验完毕,各种管口必须进行临时封堵,避免杂物进入。
○
4立管安装。在土建墙面抹灰后进行。 ○
5地板辐射采暖系统安装在土建地面已施工完,各种基准线测放完毕,敷设管道的防水层、防潮层、绝热层已完成的前提下进行。
○
6洁具在土建完成卫生间垫层后安装。然后安装支管和阀门,阀门在安装前应进行检验。
○
7给排水系统。给水系统安装完毕后应做系统试验,试验压力按照设计和规范规定进行;生活排水管要进行通球通水试验。试验合格后办理有关质量记录。
⑧各种试验完毕,开始刷油保温等工序。此时要注意不污染土建的墙面、地面等已经装饰好的部位。
(2)电气安装主要工程内容有:低压配电系统,普通照明系统,防雷及接地系统,弱电系统。
○
1土建施工时,要及时准确地完成接地焊接工作,包括水平方向和垂直方向钢筋的焊接。注意不要遗漏外引接地端子。
○
2土建各层施工浇注混凝土时,应将照明部分水平暗埋管及灯位盒准确预埋到位。 ○
3土建施工墙体时,墙内暗敷管要及时跟上,并与顶板中预埋的管子做妥善连接。 ○
4当土建主体施工结束,进入装修阶段。要把墙内的箱、盒位置调整固定好,把线穿入,并及时测量绝缘电阻。此阶段工期短,避免延误土建、装修的施工。
○
5土建、装修结束后,电气安装进行最后抢工时期,将所有电线敷设安装到位,以及电器具(包括灯具、开关、插座等)全部调试安装完。
○
6系统调试:所有系统逐一回路地检查调试,直到全部问题解决。 ○
7屋顶避雷和室外接地 屋顶避雷可在主体完工、屋面竣工前进行,做到焊接处符合要求,防腐无遗漏。 室外接地可在室外场地允许的条件下进行测量。如果基础钢筋接地电阻达不到设计要求,则应补做人工接地体。 3、工期计划安排(详见附表) 4、劳动力组织 ·管道分部
第一阶段:配合土建预埋套管及预留孔洞:
依土建施工进度,按工程师提供的预留预埋位置图纸进行,本阶段投入2人(包括各类套管的加工敷设及各系统出、入户管至±0.00,并及时做好各种隐蔽记录)。 第二阶段:安装
本阶段依土建给出的工作面拟投入人力10-15人: ①排水系统:2人/组*2组; ②给水系统:2人/组*2组; ③采暖系统:2人/组*3组;
第三阶段:试调阶段拟投入3-5人。 ·电气分部
第一阶段:配合土建预留预埋电气配管及预留箱、盒,焊接基础接地,焊接防雷引下线; 依土建施工进度,按预留预埋位置及电气施工图纸进行,本阶段投入3人。 第二阶段:安装盒、箱体
本阶段配合土建内墙安装完毕后进行,拟投入3--5人。 第三阶段:焊接避雷
本阶段配合土建在屋面做完后进行,拟投入4人20个工日,
第四阶段:配线、穿线电缆
本阶段配合土建抹灰工作完成后进行,拟投入2人/组*10组。 第五阶段:安装配电箱、柜、灯具、开关、插座 待室内装潢基本结束进行安装器具。 配电柜安装:3人/组*1组。 配电箱安装:2人/组*3组。 灯具安装:2人/组*4组。
开关、插座安装:2人/组*2组。 第六阶段:试调及验收
试调阶段拟投入7-10人,包括强电、弱电。
五、基础设施和工作环境
1、设备需要量及劳动力等供应计划
2、 安全用电技术措施
(1)临时用电设备负荷计算:
不同暂载率用电设备容量换算(交流焊弧机额定负载率0.6,交流电焊机为0.35;满负荷时的功率因数为0.87)对于电焊机:设备容量= SQR(暂载率)×铭牌额客容量X满负荷时的功率因数
交流焊弧机:Pe=32.5铭牌额定容量×SQR(0.6)×0.87=21.9KW 交流电焊机:Pe=22.5×SQR(0.35)×0.87=21KW 除照明外(取Kx=0.4 现场总需要系数,COSφ=0.6 满负荷时的功率因数COSφ)
∑Pe=21.9+2.2+0.75×3+21+2.1+0.45×2+0.8=51.15 KW
Pjs=0.4×51.15=20.46KW(有功计算负荷=需要系数X根据每台设备性质,把设备铭牌容量换算到长期工作制的设备
10
总容量)
Qjs=Pjs×tgφ=20.46×SQR(1-0.6×0.6)/0.6=27.21KW(无功计算负荷) 照明4kw
Sjs= SQR [(20.46+4)2+22.802 ] =33.44KVA视在计算负荷= SQR(有功计算负荷+无功计算页荷
2
2
)
Ijs= 33.44/[SQR(3)×0.38]= 50.82A
计算电流=视在计算负荷/SQR(3)*用电设备的额定电压*平均功率因数 公式 Sjs = SQR(3)*U*I*1 的变形
本工程用电设备如下表:
VV是聚氯乙烯绝缘,聚氯乙烯护套电缆, BV是扁状聚氯乙烯护套电缆,
RVV是聚氯乙烯绝缘,聚氯乙烯护套软电缆。后面代表是几根铜线极其截面积 1、RV 铜芯聚氯乙烯绝缘连接软电线 2、RVB 铜芯聚氯乙烯绝缘平行连接软电线
3、RVV 铜芯聚氯乙烯绝缘聚氯乙烯护套圆形连接软电线 4、RVVB 铜芯聚氯乙烯绝缘聚氯乙烯护套平行连接软电线 5、RV-105铜芯耐热105度铜芯聚氯乙烯绝缘连接软电线
① 进线方式:(三级配电两极保护)
安装施工用电由配电室引来380/220V电源,采用电缆埋地敷设方式。安装总配电箱设置在室外,低压配电线路采用放射式配电线路。如下图示意:
11
⑶ 总配电箱及分配电箱的电气配置:
根据负荷计算结果,可选择所需电器的型式及规格,保证临时用电工程在正常情况下能够安全可靠地运行,保证在故障和一定漏电的情况下可靠地分断故障和漏电电路。 以下列出安装用总配电箱(一台) 电器配置情况: 主开关(进线):DZ10-100 100A/380V 1个 漏电保护器 80A/380V 1个 出 线 :胶盖闸刀 60A/380V 2个 胶盖闸刀 30A/380V 2个 胶盖闸刀 30A/220V 4个 漏电保护器 60A/380V 1个 漏电保护器 30A/220V 1个 三相动力配电箱配置情况:(二台) 闸刀开关HK系列 30A/380V 1个 漏电保护器 30A/380V 1个 四极插座 30A/380V 2个 单相配电箱电器配置情况:(三台) 闸刀开关HK系列 30A/220V 1个 漏电保护器 30A/220V 1个 三极插座 16A/220V 3个
12
六、施工技术措施
1、主要分部分项工程施工方法、工艺措施及安全保证措施 ·电施部分
(1)配管工作:
①电气配管作为电气安装的一个关键工序,施工预埋要紧随土建顺序分区段进行,不能漏埋、错埋;严禁电气配管与水暖消防等管道相碰,电气配管与其它配管距离应按规范要求的尺寸敷设;隐蔽前进行工序交接验收:包括管路位置、规格、标高、弯度、接头、管盒固定,管口封闭处理等是否符合规范要求,并做好隐蔽记录。
②暗配管弯曲半径大于管外径的10倍,弯扁度小于0.1倍管外径,与建筑物表面的最小距离不能小于15mm。
③管进盒、箱必须使用锁紧螺母固定并加护口,严禁气焊开孔; ④塑料管连结采用专用套管加粘合剂。
⑤配管时,露天和高空作业,要注意周围环境,防止高空坠物和踏空,防止意外伤害。 (2)配线工作:
①电线、电缆穿管前,应清除管内杂物和积水。钢管配线时先戴护口后穿线,杜绝导线背扣死扣现象,零线采用淡蓝色导线,地线采用黄绿相间的双色线。 ②线盒及箱内导线预留按规范保证足够长度;
③导线与设备器具的连接按规范规定,截面为10MM2以下的单股铜芯线采用直接连接,其他规格采用压接端子连接;
13
④配线工程施工后必须进行各回路绝缘测试,保护地线连接可靠。 ⑤照明配线采用额定电压不低于750V的铜芯绝缘电线。
⑥扫管穿线时防止钢丝的弹力勾眼;俩人穿线要注意相互配合,一呼一应有节奏进行,不要用力过猛以免伤手。
(3)开关、插座、配电箱、柜安装安装:
①开关底边距地1.3m,总照明配电箱底边距地1.8米,分照明配电箱底边距地0.5米,边缘距门框150~200mm,普通插座底边距地0.3m,热水器插座距地2.3米,卫生间插座距地1.8米,且要在土建墙体抹灰前给出室内+0.5m线后方可施工;
②照明配电箱应分别设置零线与保护地线汇流排,导线在排上连接,不得绞接,并应有编
号。
③同一室内开关插座允许高度偏差为5mm。并列安装可允许偏差0.5mm,相邻两开关插座间距不小于20mm。
④单相两孔插座,接线方式是左孔零线,右孔接火线。三孔插座,接线方式是左孔零线,右孔接火线,上孔接地线。
⑤火线要经过开关后再进入灯具。
⑥开关、插座、箱的面板要紧贴墙面,端正不歪斜。
⑦安装配电箱、盘面和器具时,应防止倾倒和坠落伤人,送电试亮前,非电气工作人员禁止乱动电气器具。 (4)灯具安装;
①严禁使用木楔,应用膨胀螺栓或塑料胀管固定。 ②电气照明装置的接线应牢固,电气接触应良好。
③使用梯子靠在柱子上工作,顶端应绑牢固,并考虑防滑措施;使用人字梯必须牢固,距梯角40~60CM处要设钢索拉撑,防止劈开;不准站在梯子最上一层工作,梯凳上禁止放工具、材料。
(5)防雷与接地:
本建筑为三类防雷建筑。
在配电间内设总等电位连接板,进单元的所有金属管路采用40*4的热镀锌扁钢与连接板电焊连接。
避雷带、引下线敷设安装系高空作业,必须穿软底鞋,不得穿硬底塑料,引下线敷设前,要检查架子、跳板及防护设施,有损坏等情形不得使用,在大风和暴雨、雷电影响施工安全时,应立即停止高空作业。 (6)具体细节技术
①配合土建施工进度埋设进户管。
②配合土建砌墙留出各种线盒,配电箱的孔洞严格按规范尺寸预留。 ③土建墙体抹灰时要检查配管隐蔽前的完整情况。
④连接的灯具、开关、插座及配电箱电源端子要进行试通试亮试验。
⑤准备好各种记录并对现场交工前做最后检查,交由项目部,组织建设单位验收。 ·水卫部分
(1)通用规定:
①材料、设备必须有出厂合格证,在使用安装前应按设计要求校验规格、型号,质量符合要求方可施工。各种管材按型号、品种、规格顺序,堆放,高度不宜超过1.5米,底部应有垫木。
②管路、设备安装前必须清除内部污垢和杂物,安装中断或完毕时敞口处应临时封闭。
③给水系统竣工验收前应用水冲洗,直到清除污物为止;给水系统交付使用前应用每升水
14
含20-30毫克的游离氯的水灌满管道进行消毒,水在系统中应留置24小时以上,消毒完后用饮用水冲洗,直到清除污物为止。
④管子螺纹应完整,如有断丝、缺丝不得大于螺纹全扣数的10%。 ⑤管道穿过基础、墙壁和楼板,应配合土建预留孔洞; ⑥管道支架安装应符合下列规定: A.位置应正确,埋设平整牢固;
B.与管道接触应紧密,固定应牢固;
C.固定于建筑物结构上的支架,不允许影响结构安全; ⑦阀门安装前应作耐压强度试验,试验应以每批数量中抽查10%且不少于1个。对于给水、消火栓系统安在主干管上起切断作用的闭路阀门,应逐个作强度严密性试验。 (2)给水管道
① 一层室内给水管、排水管平行铺设时,两管最小水平净距为500mm。 ② 管道支架设置最大间距应符合下表规定
③给水横管,宜有0.003的坡度坡向泄水装置。给水立管和装有3个或3个以上配水点的支管始端,均应安可拆卸的连接件。
④系统试压:给水管的试验压力为0.75MPa,在试验压力下稳压1h,压力降不得超过0.05Mpa,然后在0.52MPa状态下稳压2h,压力降不得超过0.03Mpa,同时检查各连接处不得渗漏。
⑤系统通水:系统交付使用前要进行通水试验,观察和开启阀门、水嘴等放水。 冲洗消毒:交付使用前必须进行冲洗和消毒,水质应符合生活饮用水标准。 ⑥塑料管成品保护措施:管外缠塑料布两道。
⑦所有给水管道除梁的拐角处全部暗敷设并做不少于30mm水泥沙浆保护层。
15
(3)排水系统
1室内生活排水管道埋地及伸出屋面部分采用铸铁管,内涂水泥砂浆,石棉水泥接口。其○
它采用消声型硬聚氯乙烯排水管。屋面雨水采用外排水系统,雨水管道采用排水铸铁管。埋地管沟应平整,无突出的尖硬物,其坡度应与管道坡度相同,管沟回填土应采用细土,回填至管顶以上至少200mm处,压实后再回填至设计标高。生活污废水经化粪池处理后排入污水管网。
③成品保护:管外缠塑料布两道。 (4)卫生器具安装
①卫生器具用膨胀螺栓固定。
②卫生器具支托架安装应平整牢固,与卫生器具接触紧密。根据台面大小,洗脸盆采用L40*4的角钢做双层支架,用Φ12膨胀螺栓固定在墙上,外刷防锈漆、银粉各一遍。 ③卫生器具位置应正确,单独卫生器具坐标允许偏差10mm,成排允许偏差5m。
④卫生器具安装应平直,垂直度允许偏差不得超过3mm,水平度允许偏差2mm;单独卫生器具标高允许偏差±15mm,成排卫生器具允许偏差±10mm。
⑤地漏安装于地面最低处,其篦子顶面应低于地面5mm,地漏安装应与土建做好交底及交接。
⑥蹲便器采用自闭式冲洗阀。
⑦卫生器具在交工之前应做满水和通水试验。
⑧卫生器具属易碎物品,搬运时不要打开包装,应当轻搬轻放,防止破坏器具和不慎伤,在仓库中要成排堆放。 (5)各系统防腐要求
①金属管道及金属支架均按照设计要求及规范进行防腐。 ②管道及支架、油漆粉刷要均匀,不流坠、不漏刷。 ③特殊管道色标要注意标志清楚、醒目、美观。
·采暖部分
一、地板辐射热采暖系统安装 1、管路敷设
辐射采暖管按照蛇形盘管方式布置,加热管距墙150-200mm ,加热管间距250mm ,带阳台房间加热管间距为200mm。敷设前防水层或绝热层应平整、搭接严密,表面清理干净。敷设后的管道,排列应整齐,转弯角度、水平度、间距应一致,埋地管道不应有接头。 2、管道固定
管道固定采用专用关卡直接固定于泡沫水泥保温层上,每隔300-400mm接一个,拐弯处适加密。
3、集配装置安装
集分水器均设于壁翕内,与各房间加热管连接处设同径闸阀一个。集分水器通过表箱与主管路连接。分水器供水管距楼板层高度575mm ,回水管距楼板层高度400mm ,以便于表箱连接。 4、管道保温
主管道均作“氰聚塑”保温,楼梯间部分管道均作聚氯乙烯橡塑保温,保温层厚度为30mm ,外缠铝箔。 5、管道填充
与墙、柱交接处,应填充厚度大于或等于10 mm的软质闭孔泡沫塑料。加热管上表面填充厚度不应小于30mm.
6、在铺地板前,必须进行地热加温试验,进水温度最小为50
度,以保证采暖正常进行,
16
并应保温24小时以上,是地面干透。 三、设备安装
设备安装应严格按照《机械设备安装工程施工及验收规范》TJ231(一)-75,TJ231(五)-78执行外,还需按设备随机文件和有关要求进行。
设备安装前的准备工作:熟悉图纸资料,核对工艺平面图,核对设备地脚螺栓位置;组织班组人员进行技术交底和安全交底;编制加工品制作计划;编制安装所用机具,用料计划,并组织进场;检查验证设备基础(做基础中间交接验收记录);制作地脚螺栓和加工安装设备的垫板;编制设备进场顺序和安装的计划表;设备移交进行设备开箱检查并作好记录。履行签字认可手续(填写开箱验收检查记录);检查运输路线,布置入口运输途径。
整体安装的设备:按照设备说明书规定的安装技术要求,用标准减震形式,找好水平,吊装就位,吊装设备根据设备重量选择吊装方式,不准碰坏设备。 2、治理质量通病措施:
为提高工程质量,治理质量通病,符合节能、安全,经济合理,维修方便采取如下措施: 电气:
(1)凡所使用的设备、材料均应合格,且要有合格证明。
(2)聚乙烯管线要符合防火要求,所有敷设的电线保护管管口必须及时封堵。 (3)管进箱、盒要采用锁紧螺母固定,不得用气焊开孔。 (4)严格控制电气配管的弯曲半径及埋入深度。
(5)钢管配线先戴护口后穿线,杜绝扭结、死线现象。
(6)配线要采用不同颜色,易于区分,同一构筑物内导线颜色要统一,地线采用黄绿相间色,零线采用淡兰色。
(7)配电箱内配线要横平竖直,箱内分别设置零线和保护地线汇流排,零线和地线在汇流排上连接,不得绞接,并有编号。
(8)灯具安装严禁用木楔,一律使用螺栓。 (9)镀锌钢管敷设严禁管口对接焊。 管道:
(1)凡所使用的设备、材料均应符合合格,且要有合格证明。 (2)排水干管管道安装前要清除管腔内杂物、毛刺等。
(3)给排水干管管道安装中临时间断敞口处,要及时封堵严密,不使污杂物落入管内。 (4)排水干管穿过楼板,修理预留孔洞时,应认真用线坠找准立管中心,保证板眼位置准确、直径适宜。
(5)各种支吊架应先刷防锈漆,再安装。 地板辐射采暖系统:
搬运设备、用具、管道时,应事先清理好搬运路线的杂物,保证运输畅通。试压、运行时,不得超压试运行。
3、本工程工期紧,所以搞好施工配合和材料的及时输送是保证工程质量和工程顺利进行的首要条件。
(1)与土建专业的配合
①进场后服从总包单位的统一协调安排,在总包单位的统一规划范围内搭设临时设施。 ②预留预埋时,施工人员要认真查看土建图,查出建筑轴线、标高,明确预留预埋位置,随土建进度预留预埋。预留预埋过程中要与土建专业办理交底和交接验收,预留预埋过程中不得损坏建筑结构,如要打砸,必须征得土建结构同意,并不得损伤配筋。 ③给、排水管道穿墙、板的过洞,安装应专人负责进行孔洞修补。
17
(2)水电安装专业配合
①必须树立一盘棋的思想,服从项目部的统一管理。
②管线交叉的位置应充分协商,合理利用、排列各种管线。 ③禁止利用其它专业管线设置支架、焊接支撑件等。
(3)与装饰专业配合,与装饰专业的配合直接影响工程的观感质量,必须密切配合。 ①装饰进行前,特别是需要隐蔽的管线,要将需要充水试验的项目进行完,避免装饰进行后再试验,以免水渍污染装修,必须在装饰后进行的项目一定要采取可靠的保护措施。 ②各种箱体、开关、插座不能歪斜、灯具效果应与装潢效果协调。 (4)与建设、监理单位的配合
服从和服务于建设单位是施工单位的职责,与建设、监理单位的配合、协调是保证工程顺利进行的基本条件。
①加强与建设单位的沟通,积极为建设单位提供参考意见和建议。
②积极主动的作好技术、质量、进度方面的配合,及时办理工程变更、签证。 ③及时向建设单位提交工程进度决算,要求建设单位及时拨付工程进度款。
④尊重并积极采纳监理单位的意见和建议,加强与监理单位的沟通和配合,按照规定办理有关技术、质量方面的验收和审批。 七、施工质量保证措施 1、质量管理方针目标
质量方针:质量责任重于泰山,顾客满意高于一切。
质量管理目标:分项工程合格率100%
,内控优良率不低于80%。
2、 质量保证体系组织机构
项目部质量保证体系组织机构图
分公司质量保证体系组织机构图
18
⑴公司专职质量检查员和项目部兼职质检员对现场跟踪检查,发现问题要当面提出,有权制止违章施工及不合理施工,有权责令整改和返工。
⑵工地施工负责人必须指导工人严格按规范施工,做好自检互检和各项记录,坚持上道工序不验收,下道工序不施工的原则,层层把好质量关。 ⑶公司不定期进行检查指导,落实责任制。
⑷要注意设备、材料、半成品的保护工作,做到安装结束后不损坏建筑产品整体结构及外观质量
3、以顾客为关注焦点
分公司技术经理负责组织本工程施工合同的交底,项目部认真学习施工合同合合同交底内容。当因设计变更、工艺变动及顾客提出新的要求时,项目负责人按照《招标文件及合同评审程序》重新进行评审后报分公司,分公司协助项目部与建设单位签订补充协议,并及时通知有关部门,经营发展部和分公司合同管理部门存档备案;项目部在合同执行过程中遇到某些条款履行困难或无法履行时,应及时向分公司报告,由分公司与经营发展部协商,必要时与顾客联系共同解决。分公司合同管理员和项目部负责合同的保管和使用,工程交工后,合同及合同评审由合同管理员统一存档管理。
开工阶段,项目部负责人向总包及顾客递交项目部成员组成及分工,如有变动应及时通知相关单位。
项目施工阶段,项目技术负责人应按照合同规定的时间向顾客报送进度及月份完成工作量结算,并返回回执报妥善保存。
项目部通过工程例会、工程检查、与顾客的联系和沟通等形式及时收集顾客意见和建议,做好顾客满意度调查并反馈至分公司,对顾客抱怨应及时采取措施解决。
服务应执行QWJ/Ⅱ752-2002《服务程序》。分公司负责工程服务的管理,项目部负责服务的实施,按照《质量管理条例》和施工合同进行工程的回访、保修和投诉处理。 4、文件要求
① 文件管理
由项目技术负责人负责,执行QWJ/Ⅱ423-2002《文件管理程序》。拟用于本工程的
19
② 质量记录
执行QWJ/Ⅱ424-2002《记录管理控制程序》。项目部技术员负责施工技术资料的整 理、收集、编目、保管;保管员负责物资验证、标识等整理、收集、保管;项目负责人负责顾客及上级主管部门关于质量方面的记录性文件的整理、保管。 拟用于本工程的隐蔽工程验收及施工试验记录:
电气:
通风空调:
拟用于本工程的检验批质量验收记录:
电气动力、照明、弱电:
拟用于本工程的环境安全记录清单:
5、人力资源控制
工程开工前,项目负责人对项目部人员进行合同及合同交底的学习,施工技术员组织施工人员学习图纸,组织新技术、新工艺的学习、培训;项目负责人组织对施工人员的安全教育和培训。班组长负责对施工人员进行施工安全技术培训教育合班前班后安全教育,培训应按照QWJ/Ⅱ620-2002《培训程序》进行。
6、物资控制(采购)
项目部根据工程进度编制“材料采购计划”,报分公司材料部门进行物资采购,分公司和项目部制定搬运方案,搬运人员负责物资搬运;仓库保管员对负责进入仓库的物资进行验收,项目部保管员按照 《物资控制程序》和QWJ/ⅢJS.09-1999《原材料取样检验和施工试验(安装部分)》负责对现场物资的标识、贮存、防护和不合格品的处置;并协助公司材料部门做好直拨工地材料的验收。项目部配合公司材料部门按照相关文件的规定做好材料的报验工作。
7、机械设备和周转器材及监视、测量装置的管理、控制
执行《设备管理标准》和《周转器材管理规定》及《计量管理程序》,设备进场应 有分公司设备员会同项目设备管理人员共同验收并保存进场验收记录和台帐,项目班组长负责设备的管理,使用人员负责设备的日常保养,发生机械设备故障应通知分公司设备员组织维修。项目部、分公司要经常检查机械设备的使用管理情况。监视和测量装置应由计量员负责周检,做好发放台帐并经常检查计量器具的完好性、准确性。
8、施工过程控制
根据QWJ/Ⅱ751-2002《施工过程控制程序》的规定,对本工程施工过程的控制做如下要求:
分公司技术经理或委托项目负责人向项目部成员进行合同交底并在施工日志中做好记录;项目部根据施工总进度计划编制月进度计划,确定资源,施工过程中特种作业人员要持证上岗;分项工程施工前,技术人员按照质量计划/施工组织设计、施工方案并结合有关的标准、规范、法规编制书面安全技术交底,交底中要明确施工产品的防护措施,交底记录要有施工员、班组长的签字,班组长对班组人员进行口头交底;设计变更要进行交底并做好记录;项目部要定期组织项目技术员、材料员、质检员进行监督检查施工情况;
项目经理加强与顾客的联系和沟通,及时反馈和处理顾客意见。
C关键工序的控制:
电气配管作为电气安装的一个关键工序:敷设电线保护管时,管路固定牢固,连接处用专用套管,涂胶均匀,并绑扎可靠,管头封堵严密;对易受机械损伤的地方及过梁板处
加套管保护,隐蔽验收前对照图纸查看一遍,以防有遗漏及错误的地方。
卡箍安装必须遵循先装大口径、总管、立管,后装小口径、支管的原则。安装过程中不可跳装,必须按顺序连续安装,以免出现段与段之间连接困难和影响管路整体性能。 (1)检查橡胶密封圈是否完好。
(2)将另一根钢管靠近已卡上橡胶密封圈的钢管端部,两端处应留有一定的间隙,间隙应符合标准要求。
(3)将橡胶密封圈套在另一根钢管顶端,使橡胶密封圈位于接口中间部位,并在其周 边涂抹润滑剂(洗洁精或肥皂水)。
(4)两根管道的轴线应对正,并将管内杂物清除。
(5)用手力压紧上下卡箍的耳部,并用木榔头槌紧卡箍凸缘处,将上下卡箍靠紧。
(6
)在卡箍螺栓位置穿上螺栓,并均匀拧紧螺母,防止橡胶密封圈起皱。 (
7
)检查确认卡箍凸边全圆周边卡进沟槽内。
9、产品的监视和测量
按照QWJ/Ⅱ824-2002《产品监视和测量程序》,分公司和项目部负责对工程形成的成品、半成品的质量进行检验和试验;各分项工程严格执行班组自检、互检、交接检,项目经理组织工序交接验收,施工技术员组织隐蔽验收并通知公司和顾客参加。
①检验批质量验收由项目经理组织项目质检员、施工技术员、班组长检查验收后,填写“检验批质量验收记录”,提交监理工程师组织检验批的最终验收。
②分项工程质量验收由项目部自检合格后,填写“分项、工序、样板预验申请表”,报公司质检员,由公司检查验收。对于必检分项,在分公司检查验收合格后,还应通知集团公司验收。分项验收合格,填写“分项、工序、样板验收单”。而后,项目部填写“分项工程验收记录”,提交监理工程师组织分项验收。
③分部工程质量验收由项目经理组织生产科长、技术经理、分公司质检员共同验收。验收合格,填写“分部(子分部)工程质量验收记录”,提交总监理工程师验收。
④竣工验收由土建公司组织。竣工验收前,必须确保我公司工程承包范围内的工程施工完毕且工程质量满足合同规定。
10、分析改进
对于施工过程中出现的不合格品,按照QWJ/Ⅱ830-2002《不合格品控制程序》进行处置。
一般和轻微不合格品的评审和处置由分公司和项目部负责,项目部、分公司、技术质量部下达“工程质量存在问题整改通知单”交施工班组长、项目部组织处置,项目质检员、分公司质检员验证。
对于不合格/潜在不合格采取纠正/预防措施,按照QWJ/Ⅱ850-2002《纠正/预防措施程序》进行。
项目部按照QWJ/Ⅱ840-2002《数据分析程序》负责项目部内各种信息的收集、整理、分析,确定项目质量管理的适宜性和有效性,并反映、识别可持续改进的机会。用于本 程的数据分析方法:
八、
施工过程中要认真贯彻“安全第一,预防为主”的方针,切实抓好安全生产的管理工作。
安全管理目标:加强对施工人员的教育与监督,杜绝重大伤亡事故与重大火灾事故的发生,最大限度的减少轻伤事故,全年负伤事故频率严格控制在5‰以内。
环境管理目标:施工工程中要求施工人员以节约与再利用为中心,力争做到处处事事讲环保讲节能。 (一)组织管理
1. 成立环境安全领导小组 组 长: 组 员: 职责分工
① 组长负责组织对项目施工人员的安全教育,每周一次组织对项目的环境安全进行检查,负责组织环境安全事故的急救工作,负责事故的调查分析和事故报告,依据有关标准进行考核并保存有关记录。
② 组员负责对班组施工进行环境安全方面的交底并监督落实,负责环境安全资料整理,参与事故的调查分析。
③ 组员负责对本班组人员的安全教育,负责环境安全施工技术措施的具体实施,
参与事故的调查分析处理,负责事故预防措施的落实。
(二)、安全管理
本工程存在的安全因素:(1)火灾、爆炸 (2)机械伤害(3)高空坠落(4)物体打击(5)触电(6)中毒(7)消防保卫(8)交通事故。
发生以上事故要保护好现场,及时组织抢救伤员并立即向上级报告。 1、油漆存放、电焊、气割作业、电气存在火灾爆炸隐患。 采取的预防措施:
(1)油漆应单独存放,仓库应远离生活区,要求室内温度不宜过高,室内通风良好,悬挂“严禁烟火”的警示牌,配备一定数量的灭火器、灭火砂等消防设施。
(2)油漆在堆放时要整齐,分类堆放,堆放高度不宜过高,不超过三层,避免最底部的包装罐受压破裂,造成油漆外溢。及时整理堆放区,摆放整齐,清理杂物。
(3)各类油漆包装、标识应完好。
(4)保管员要具有较高的责任心,掌握油漆的危害性,具有一定的消防知识,会使用灭火器等消防器材。
(5)严禁任何人在任何地点使用油漆、油渣作引燃品,严禁任何人在仓库内吸烟。
(6)发现油桶破损、油漆泄漏,保管员应组织人员将泄漏的油漆桶临时堵好并向项目部汇报,移出仓库,将油漆盛装在完好的容器内。
(7)电焊施焊、气割时,其周围10米内不准有易燃易爆物品,不准与油漆工并行作业。并采取良好的通风措施。
(8
)施焊、气割完毕或焊工离开现场时,必须确认用火熄灭,周围无隐患,方可离
开现场。
(9)装卸乙炔、氧气瓶时应轻装轻卸,严禁抛、滑、滚、碰。
(10)氧气、乙炔等化学危险物品,应单独存放,做好标识。存放氧气、乙炔的间距不得少于5m,不得在高温下露天存放。
(11)使用氧气,液化气,乙炔时,其间距不得少于10m。 (12)乙炔瓶,氧气瓶均应设有安全回火防止器,橡皮管连接处需用扎头固定,防止乙炔管脱落漏气。
(13)氧气瓶严防沾染油脂,有油脂衣服,手套等禁止与氧气瓶、减压阀、氧气软管
接触。
(14)施工现场临时用电应经常巡检,对线路、电器元件的完好性进行检查,发现问题立即解决。
采取的应急措施:如有火灾发生,项目部及时组织现场人员进行抢救,充分利用现场消防设施,火势较大现场无力扑救时应立即拨打火警电话(119),讲清火险发生的地点、情况、报告人及单位等,并派专人到路口迎接。灭火时要注意自我保护,注意结构在燃烧时可能造成的坍塌。氧气、乙炔造成回火时,应及时关闭气源用干粉灭火器或用浸湿的被子将氧气、乙炔瓶盖住,并及时疏散现场人员到远离发生区地带,以免过多人员发生伤亡。电气发生火灾时应先切断电源,再使用砂土、二氧化碳灭火器灭火,不得用水灭火。 2、套丝机、无齿锯、电焊机、电锤、电钻的使用存在机械伤害。
采取的预防措施:
施工人员要遵守施工机械设备操作规程及有关的管理制度,施工机械应悬挂操作规程牌,机械设备经设备管理员验收合格后方可使用。
采取的应急措施:发生伤害时,施工负责人及时组织人员采取抢救措施或及时拨打急救电话120,抢救时应注意不要搬抬伤者受伤部位,当流血时应采取绑扎措施,防止流血过多,将伤害降低到最低限度。
3、梯子的使用、高空灯具安装、屋顶避雷施工及施工过程中的行走存在高空坠落危险。
采取的预防措施:
(1)使用梯子时,应检查中间拉撑是否牢固。严禁梯顶作业或二人同时在一个梯子上作业,梯子作业应有人监护。
(2)梯子与地面夹角为60º-70º,在光滑地面上使用时底角要有防滑措施。 (3)灯具安装用的平板车要有防护措施,四周应设置围栏。
(4)高空作业穿着要灵活,禁止穿硬底鞋、高跟鞋、塑料底鞋和带钉的鞋。 (5)作业人员要注意临边、洞口的防护,不得倒行,以免坠落。
(6)避雷作业应采取防护措施,有人监护。大风、雷雨天气严禁在屋顶从事避雷作业。
采取的应急措施:高空坠落时,应及时采取抢救措施,及时送往医院或拨打急救电话120。注意摔伤及骨折部位的保护,避免因不正确的抬运使骨折错位造成二次伤害。
4、交叉作业、材料设备装卸车存在物体打击危险。
采取的预防措施:
(1) 项目部、班组要合理安排生产,尽量避免复杂的交叉作业。
(2) 交叉作业时,施工人员要正确佩戴好安全帽,避免在上下同一垂直面上作业。
(3) 必须垂直交叉作业时,上部施工为下部施工提供可靠的隔离防护措施,确保
下部施工人员安全,下部人员在隔离设施未完善前不得开始施工。
(4)搬运工应合理装卸材料,保证安全运输,严禁超载、超高、超宽、超长。管材
严禁抛、摔,以免滚砸伤人员,管材堆放要平稳。
(5)搬运机器,必须查明重量、尺寸、装卸地点后,制定方案。按照方案操作。
(6)车辆未停稳,严禁人在车辆上操作 。车辆行驶时,严禁人在拦板上或车顶高处,
更不准站在物件的顶头,防止急刹车物件往前突然移动而扎伤人,装运构件,必须选好垫
头木,防止物件倒坍造成事故。
(7)车辆进出照顾前后,倒车、转弯、领车、正常行驶时应注意前后左右马路上的
动态。
采取的应急措施:发生物体打击时,及时组织人员进行抢救,临时包扎伤口并拨打120。
5、机械设备的使用、临时用电、通电调试存在触电危险。
采取的预防措施:
(1)进入现场临时用电设备要按照一机一闸一漏一箱配电。
(2)操作前应检查所有机械电源开关及线路是否良好,金属外壳应有安全可靠接地
或接零,进出线应有完整的防护罩,进出线端连接牢固。
(3)注意安全用电,电线不准乱拖乱拉,电源线均应架空扎牢,潮湿场所、检查用
电设施时应穿戴绝缘鞋、绝缘手套。
(5)检修设备机械时,应拉闸断电,严禁带电进行检修作业。
(6)停电后,应及时关闭机械设备的开关。
(7)电工通电调试时应进行安全技术交底并遵循安全用电管理规定。
采取的应急措施:触电事故发生时,应用木棒将电线挑离身体,并及时拉闸断电,及
时拨打急救电话120,受伤人员呼吸停止时应及时进行人工呼吸或胸外心脏挤压。
6、油漆配兑、粉刷及食物有中毒危险。
采取的预防措施:
(1)搬运油漆时要轻拿轻放,不得扔放,避免摔坏包装罐体造成油漆泄漏。
(2)油漆配兑要在通风处进行。
(3)操作人员应佩带好口罩、手套、防止有害气体和粉尘的吸入。
(4)使用干净卫生的食品,严禁用非实用性塑料制品盛放食品。
(5)施工现场应供应开水,饮水器具要卫生。
采取的应急措施:油漆中毒时及时将中毒人员搬到通风处,食物中毒时及时通知医务
人员,严重时,直接拨打120。
7
、施工现场库房、施工半成品、施工临时设施等存在被盗、被破坏等因素,需要加强
30
消防保卫工作。
采取的预防措施:
(1) 成立保卫消防小组
组长:
组员:
(2)施工材料的存放、保管。加强巡视,工具使用完毕后及时入库。
(3)易燃易爆物品存放应有良好的通风,仓库照明等电器应符合防火规定。
(4)施工现场应配备灭火器、灭火砂等消防器材。
采取的应急措施:施工现场库房、施工半成品、施工临时设施等存在被盗、被破坏,
及时报告分公司,并保护好现场。
8、本工程为远地施工,施工与工作人员存在发生交通事故的因素,需加以注意。
采取的预防措施:
(1)时刻提醒施工与工作人员注意交通安全,首先从自己开始遵守交通规则,其次坚
决乘坐有保障的车辆,不随便搭无安全保障的车辆往来工地。
(2)建议长期在工地施工的人员住宿,减少往来交通。
(三)环境保护
本工程存在的环境因素包括:(1)噪声污染(2)固体废弃物污染(3)粉尘污染(4)
危险品污染(5)废水排放
1、无齿锯使用、电锤使用存在噪声污染。
采取的措施:
(1) 尽量将无齿锯、电锤等小型电动设备安置在边角,人少场所。
(2) 无齿锯防护罩要完整,紧固牢固,物件要加持牢固。
(3) 电锤作业应佩戴耳塞。
(4) 要经常检查小型机电设备的运行情况,不准带病运行。
(5) 科学合理的安排作业时间,把夜间使用小型电动机电设备的时间,频次控制在
最低限度。
2、电气焊产生的焊渣焊条头;塑料废管头;穿线产生的电线头;机械维修保养产生的废
旧油手套;废办公用品;废旧油漆桶;食物等存在固体废弃物污染。
采取的措施:
(1)对电气焊作业产生的焊渣焊条头,切割机、台钻、手电钻等小型电动设备操作中产
生的碎屑,穿线产生的电线头,要日积日清,放置在施工现场的建筑垃圾堆放点。
(2)严禁任何人在任何地方焚烧生产、生活废弃物。
(3)机械维修保养产生的废旧油手套、油漆桶及废旧法兰填料属危险废物,应单独存放,
做好标识。连同办公用品的废计算器、废磁盘、废圆珠笔芯等,在分公司的统一安排组织
下集中处置。
(4)食物等固体废弃物应放置在指定位置由专人统一处理。
31
3、电锤作业;无齿锯作业;保温作业;剔槽作业;办公卫生;车辆场区内运输易产生粉
尘污染。
采取的措施:
(1)使用电锤,无齿锯等小型机电设备在建(构)筑物上钻孔,割槽的操作工人应佩带
口罩,防止粉尘,扬尘吸入体内。
(2)车辆场区内运输时,应清除轮胎上的泥土。
(3)对散落在现场的粉尘,要及时清扫或用水浸的扫帚清扫,并置放于施工现场建筑垃
圾堆放点。
4、仓库油漆、稀料;机械设备维修保养;PVC管粘接剂;车辆油箱存在危险(危险品易
挥发、泄露、渗漏)。
采取的措施:
(1)搬运油漆时要轻拿轻放,不得扔放,避免摔坏包装罐体造成油漆泄漏。
(2)油漆在堆放时要整齐,按类堆放,堆放高度不宜过高,不超过三层,避免最底部的
包装罐受压破裂,造成油漆外溢。
(3)机械设备维修时应首先清理废油,含油铁屑的过滤废油应回收利用或再生。
(4)车辆油箱应经常检查,发现漏油应及时修理好,其上的灰尘应经常清理;PVC粘接
剂易挥发,有刺激性气味,不得用手直接接触,戴好口罩。
(四)、文明施工管理
1、施工现场的临时设施、材料堆放。
(1)各种大小临时设施和各种材料、半成品堆放整齐,各种标识齐全,规格一致。
(2)各种管材按型号、品种、规格顺序,堆放,高度不宜超过1.5米,底部应有垫木。
(3)带丝口配件,要包装整齐,防止磕碰和潮尘。
2、施工现场及办公区卫生管理。
(1)制定文明施工管理制度,划分区域,明确管理责任人,实行挂牌制,做到现场整洁。
(2)现场临时水电要有专人管理,不得长流水,长明灯。
(3)施工现场场地平整,道路坚实,有排水设施,地下管道施工完毕后要及时回填平整。
(4)工人操作地点周围必须清洁整齐,做到活完脚下清,工完场地清。
(5)要有严格的成品保护措施,严禁损坏污染成品,堵塞管道。要设置临时便桶,严禁
在建筑物内大小便。
(6)不同垃圾分开放置。
3、个人卫生及防护用品的使用。
(1)工人进入施工现场必须戴好安全帽。
(2)登高超过两米必须佩带安全带。
(3)在灰尘较多场所及刷油漆时,合理使用防尘口罩。
(4)噪声较大时要使用耳塞、耳罩等防护用品。
九、工期保证措施
32
1.技术员根据每月的形象进度提出详细的材料供应计划,材料部门及时购买并及时供应到
施工现场。
2.加强材料、设备的进场验收和劳动力的合理调度,确保各生产要素的合理配置和调度,
提供一切有利条件,确保本工程保质保量完工。
3.加强过程质量控制,严格遵守工序交接验收制度,加强内部各工种、外部各单
位之间的施工配合,穿插流水作业要进行合理安排,及时进行沟通,避免返工、窝工现象。
4.严格按照设计图纸、施工验收规范、施工方案、技术交底施工,及时跟踪检查
工程质量,做好施工成品和半成品的保护工作。
十、降低成本措施
1. 现场施工人员充分熟悉工程特点,施工范围、工艺流程,复核建筑坐标、设备位置,做
好施工准备,减少不必要的材料、人工消耗,降低成本。
2.
班长合理安排组织作业人员、作业计划,均衡生产,防止出现窝工,
材料部门保证按计划供料,防止停工待料现象。减少二次运输和运输次
数。
3. 合理安排施工顺序,协调同其它工程间的协作关系,避免不必要的返
工,严把质量关,合理用料,降低废品率,提高材料利用率,做到省时、
省力、省材料。
4. 加强材料管理,定期进料,防止材料积压,对材料加强验收,从数量、
质量、规格型号严格把关,防止不合格材料进场造成经济损失,机械设
备合理使用,使用完及时退回仓库,节约台班费用。
5. 采购材料,择优进货,货比三家。
6. 施工中积极推行新工艺、新材料、新机具,降低成本。7. 开展增收节
支活动,对下脚料、废料及时回收。 十一、施工平面布置图(按土建施工平面现场确定)
33